SCHEDULE 10PROCEDURE FOR ORDERS TERMINATING LISTED BUILDING PARTNERSHIP AGREEMENTS
PART 1ORDERS MADE BY PLANNING AUTHORITIES
I11Requirement for confirmation by Welsh Ministers
1
An order under section 115 made by a planning authority does not take effect unless it is confirmed by the Welsh Ministers.
2
Where a planning authority submits an order to the Welsh Ministers for confirmation, it must serve notice of the submission of the order on—
a
the other parties to the listed building partnership agreement,
b
any other person occupying the listed building, or the part of a listed building, to which the agreement relates under a lease granted or extended for a fixed term that has at least 2 years left to run, and
c
any other person the authority thinks will be affected by the order.
3
The notice must specify the period within which a person on whom it is served may make a request in writing to the Welsh Ministers for an opportunity to appear before and be heard by a person appointed by the Welsh Ministers.
4
If a person on whom the notice is served makes such a request within that period, before confirming the order the Welsh Ministers must give such an opportunity to that person and each planning authority that is a party to the listed building partnership agreement.
5
The period specified under sub-paragraph (3) must be at least 28 days beginning with the day after the day the notice is served.
6
The Welsh Ministers may confirm the order with or without modifications.