126Effect of granting listed building consent on enforcement noticeE+W
This section has no associated Explanatory Notes

(1)This section applies if, after an enforcement notice has been issued, listed building consent is granted under section 89(2)—

(a)authorising any works to which the notice relates that have been carried out in breach of section 88, or

(b)authorising works which involve a breach of a condition subject to which a previous consent was granted.

(2)The notice ceases to have effect (or does not take effect) so far as it—

(a)requires steps to be taken that are inconsistent with the authorisation of the works, or

(b)requires steps to be taken for complying with the condition.

(3)The fact that an enforcement notice has wholly or partly ceased to have effect by virtue of this section does not affect the liability of any person for an offence in respect of a previous failure to comply with the notice (see section 133).

Commencement Information

I1S. 126 not in force at Royal Assent, see s. 212(2)