PART 2MONUMENTS OF SPECIAL HISTORIC INTEREST
CHAPTER 3CONTROL OF WORKS AFFECTING SCHEDULED MONUMENTS
Grant of scheduled monument consent subject to conditions
I118Power to grant consent subject to conditions
1
Scheduled monument consent may be granted subject to conditions.
2
A condition may, for example—
a
impose requirements with respect to the way in which or the persons by whom the works or any of the works are to be carried out;
b
require that a person authorised by the Welsh Ministers be given an opportunity, before any works start, to examine the monument and its site and to carry out such excavations as the Welsh Ministers consider to be desirable for the purpose of archaeological investigation.