PART 2E+WMONUMENTS OF SPECIAL HISTORIC INTEREST

CHAPTER 3E+WCONTROL OF WORKS AFFECTING SCHEDULED MONUMENTS

Grant of scheduled monument consent subject to conditionsE+W

19Condition about period within which works must startE+W

(1)Scheduled monument consent must be granted subject to the condition that the works to which it relates must start before the end of a period which is specified in the condition and begins with the day the consent is granted.

(2)If consent is granted without the condition required by subsection (1), it is to be treated as having been granted subject to the condition that the works to which it relates must start within 5 years beginning with the day it was granted.

(3)This section does not apply to—

(a)scheduled monument consent which provides that it ceases to have effect at the end of a period specified in the consent (irrespective of whether any works have started),

(b)consent granted under section 13(2) (consent for works already carried out), or

(c)consent granted by a scheduled monument partnership agreement or a management agreement (see sections 25 and 51).