xmlns:atom="http://www.w3.org/2005/Atom"

SCHEDULELICENSING SCHEMES

10For a period beginning not less than 21 days before the date on which a licensing scheme takes effect and continuing for so long as the scheme remains in force, the Corporation must—

(a)on its website, publish the scheme and state—

(i)the manner in which an application for a licence may be made; and

(ii)the effect of section 10(4); and

(b)on notices posted in the open space, provide information sufficient to bring the scheme to the general attention of persons resorting to the open space, including—

(i)the date on which the licensing scheme takes effect;

(ii)the activities to which it applies;

(iii)the website on which the licensing scheme may be viewed;

(iv)the manner in which an application for a licence may be made; and

(v)the effect of section 10(4).