Determination of completion dayE+W

3(1)If the person on whom a completion notice is served agrees in writing with the authority by whom the notice is served that a day specified by the agreement shall be the completion day in relation to the building, that day shall be the completion day in relation to it.E+W

(2)Where such an agreement as is mentioned in sub-paragraph (1) above is made, the completion notice relating to the building shall be deemed to have been withdrawn.

4(1)A person on whom a completion notice is served may appeal to a [F2valuation tribunal] against the notice on the ground that the building to which the notice relates has not been or, as the case may be, cannot reasonably be expected to be completed by the day stated in the notice.E+W

(2)Where a person appeals against a completion notice and the appeal is not withdrawn or dismissed, the completion day shall be such day as the tribunal shall determine.

[F3(3)In this paragraph “valuation tribunal” means—

(a)in relation to England: the Valuation Tribunal for England;

(b)in relation to Wales: a valuation tribunal established under paragraph 1 of Schedule 11.]

Textual Amendments

F2Words in Sch. 4A para. 4(1) substituted (6.3.1992) by 1992 c. 14, s. 117(1), Sch. 13 para. 83(2) (with s. 118(1)(2)(4))

5E+WWhere a completion notice is not withdrawn and no appeal under paragraph 4 above is brought against the notice or any appeal under that paragraph is dismissed or withdrawn, the day stated in the notice shall be the completion day in relation to the building.