SCHEDULE 5E+WLicences under Parts 2 and 3: procedure and appeals

Part 1E+WProcedure relating to grant or refusal of licences

Meaning of “the end of the consultation period”E+W

12(1)In this Part of this Schedule “the end of the consultation period” means the last day for making representations in respect of the matter in question.E+W

(2)The end of the consultation period must be—

(a)in the case of a notice under paragraph 1 or 5, a day which is at least 14 days after the date of service of the notice; and

(b)in the case of a notice under paragraph 3, a day which is at least 7 days after the date of service of the notice.

(3)In sub-paragraph (2) “the date of service”of a notice means, in a case where more than one notice is served, the date on which the last of the notices is served.

Commencement Information

I1Sch. 5 wholly in force at 16.6.2006; Sch. 5 not in force at Royal Assent see s. 270(4)(5); Sch. 5 in force for E. at 6.4.2006 by S.I. 2006/1060, art. 2(1)(a) (with Sch.); Sch. 5 in force for W. at 16.6.2006 by S.I. 2006/1535, art. 2(a) (with Sch.)