SCHEDULE 31Extension of planning permission for statutory undertakers
Condition of extended planning permission
2
1
Planning permission granted by virtue of paragraph 1 is subject to the condition that development is carried out in accordance with such requirements as the Secretary of State may by notice to the developer specify for the purpose of—
a
avoiding a breach of an undertaking given by the Secretary of State to the Select Committee of either House of Parliament to which the High Speed Rail (West Midlands - Crewe) Bill was committed, or
b
securing that the environmental effects of carrying out the development are not materially different from those envisaged by the statement by virtue of which paragraph 1(1)(b) applies.
2
The power conferred by sub-paragraph (1) is exercisable after, as well as before, development is commenced.
3
The power conferred by sub-paragraph (1) includes power, exercisable in the same manner, to vary or revoke a notice under that sub-paragraph.
4
The condition imposed by sub-paragraph (1) is in addition to any condition to which the planning permission may be subject apart from this paragraph.