xmlns:atom="http://www.w3.org/2005/Atom" xmlns:atom="http://www.w3.org/2005/Atom"

PART 5U.K.Water

Storm overflowsU.K.

84Report on elimination of discharges from storm overflowsE+W

(1)The Secretary of State must prepare a report on—

(a)the actions that would be needed to eliminate discharges from the storm overflows of sewerage undertakers whose areas are wholly or mainly in England, and

(b)the costs and benefits of those actions.

(2)The Secretary of State must publish the report before 1 September 2022.

(3)The report must be laid before Parliament once it is published.

Commencement Information

I1S. 84 in force at 9.1.2022, see s. 147(2)(j)