SCHEDULE 7U.K.Discretionary exclusion grounds

Acting improperly in procurementU.K.

13(1)A discretionary exclusion ground applies to a supplier if a decision-maker considers that—

(a)the supplier has acted improperly in relation to any procurement, and

(b)in so doing, the supplier put itself at an unfair advantage in relation to the award of a public contract.

(2)A supplier might act improperly in relation to a procurement by—

(a)failing to provide information requested by the contracting authority;

(b)providing information that is incomplete, inaccurate or misleading;

(c)accessing confidential information;

(d)unduly influencing the contracting authority’s decision-making.