xmlns:atom="http://www.w3.org/2005/Atom" xmlns:atom="http://www.w3.org/2005/Atom"

PART 4U.K.Management of public contracts

Prospective

Modifying public contractsU.K.

77Publication of modificationsU.K.

(1)Before the end of the period of 90 days beginning with the day on which a contracting authority makes a qualifying modification under section 74(1), the authority must publish a copy of—

(a)the contract as modified, or

(b)the modification.

(2)A “qualifying modification” is a modification—

(a)in respect of which the contracting authority is required to publish a contract change notice under section 75, and

(b)which modifies, or results in, a public contract with an estimated value of more than £5 million.

(3)Subsection (1) does not apply in relation to a modification of a contract that—

(a)was awarded by a devolved Welsh authority, unless it was awarded as part of a procurement under a reserved procurement arrangement, or

(b)was awarded as part of a procurement under a devolved Welsh procurement arrangement.

(4)A Minister of the Crown may by regulations amend this section for the purpose of changing the financial threshold.

Commencement Information

I1S. 77 not in force at Royal Assent, see s. 127(2)