SCHEDULES

SCHEDULE 13FOR PROTECTION OF BRITISH WATERWAYS BOARD

Interpretation

2

In this Schedule—

  • “the Board” means the British Waterways Board;

  • “the Board’s network” means the Board’s network of waterways;

  • “construction”, in relation to any specified work or protective work, includes—

    1. a

      the execution and placing of that work; and

    2. b

      any relaying, renewal or maintenance of that work as may be carried out during the period of 24 months from the completion of that work; and

  • “construct” and “constructed” have corresponding meanings;

  • “detriment” means any damage to a waterway or any other property of the Board and, without prejudice to the generality of that meaning, includes—

    1. a

      any obstruction of, or interference with, or hindrance or danger to, navigation or to any use of a waterway;

    2. b

      the erosion of the bed or banks of a waterway, or the impairment of the stability of any works, lands or premises forming part of a waterway;

    3. c

      the siltation of a waterway or the deposit of materials in, so as to materially damage the waterway;

    4. d

      the pollution of a waterway;

    5. e

      any material alteration in the water level of a waterway, or material interference with the supply of water thereto, or drainage of water therefrom;

    6. f

      any material harm to the ecology of a waterway (including any material adverse impact on any site of special scientific interest comprised in the Board’s network); and

    7. g

      any interference with the exercise by any person of rights over the Board’s network;

  • “the engineer” means an engineer appointed by the Board for the purpose in question;

  • “plans” includes sections, designs, drawings, specifications, soil reports, calculations, descriptions (including descriptions of methods of construction) and programmes;

  • “protective work” means a work constructed under paragraph 7(3)(a);

  • “specified work” means so much of any of the authorised works as is situated upon, across, under, over or within 15 metres of, or may in any way affect a waterway; and

  • “waterway” means Canning Dock, Salthouse Dock, Wapping Basin and Duke’s Dock in the city of Liverpool and includes any works, lands or premises belonging to the Board, or under its management or control, and held or used by the Board in connection with Canning Dock, Salthouse Dock, Wapping Basin and Duke’s Dock.