PART 2Subsystems

Fees payable to the Safety AuthorityI113

1

A person applying to the Safety Authority for authorisation of a project subsystem under regulation 4 shall be liable to pay such fee to the Safety Authority as the Safety Authority may charge in respect of the Safety Authority’s work in relation to the application.

2

The fee payable under paragraph (1) shall—

a

not exceed the sum of the costs reasonably incurred by the Safety Authority in carrying out the work referred to in paragraph (1); and

b

be payable within 30 days from the date of the invoice that the Safety Authority has sent or given to the person who is required to pay the fees, such invoice to include a statement of the work done and the costs reasonably incurred including the period to which the statement relates.

3

A fee payable under this regulation shall be recoverable as a civil debt.

4

Failure to pay a fee under this regulation shall not constitute an offence under these Regulations.

5

This regulation shall not apply in relation to the Channel Tunnel system and the Intergovernmental Commission.