SCHEDULES
MODIFICATION OF COMPENSATION AND COMPULSORY PURCHASE ENACTMENTS FOR CREATION OF NEW RIGHTS
FOR PROTECTION OF ELECTRICITY, GAS, WATER AND SEWERAGE UNDERTAKERS
Removal of apparatus and construction of alternative apparatus by the promoter
Retained apparatus: protection and plan approval
20.Not less than 56 days before commencing to construct or...
22.The promoter must not commence the construction or renewal of...
23.Any approval of the specified undertaker required under paragraph 22—...
27.Nothing in paragraph 20 or 26 precludes the promoter from...
28.The promoter is not required to comply with paragraph 20...
29.Nothing in paragraph 28 entitles the promoter to carry out...
FOR PROTECTION OF RAILWAY INTERESTS
1.The following provisions of this Schedule have effect, unless otherwise...
2.In this Schedule— “construction” includes execution, placing, alteration and reconstruction...
3.(1) Where under this Schedule Network Rail is required to...
4.(1) The promoter must not exercise the powers conferred by...
5.(1) The promoter must before commencing construction of any specified...
7.The promoter must— (a) at all times afford reasonable facilities...
8.Network Rail must at all times afford reasonable facilities to...
9.(1) If any permanent or temporary alterations or additions to...
10.The promoter must repay to Network Rail all reasonable fees,...
11.(1) In this paragraph— “EMI” means, subject to sub-paragraph (2),...
13.The promoter must not provide any illumination or illuminated sign...
14.Any additional expenses which Network Rail may reasonably incur in...
15.(1) The promoter must pay to Network Rail all reasonable...
18.The promoter and Network Rail may, subject in the case...
19.Nothing in this Order, or in any enactment incorporated with...