The Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014

Control of Pollution Act 1974

13.—(1) Where a local authority is acting further to Section 60(4) of the Control of Pollution Act 1974 in relation to the construction of the authorised project and works before completion of construction then that local authority shall also have regard to the noise levels referred to in the Environmental Statement for each construction site and the principles of the Code of Construction Practice.

(2) Sections 60(7) and 61(7) of the Control of Pollution Act 1974 shall not apply in relation to the authorised project.

(3) Underground tunnelling works shall be regulated by Sections 60 and 61 of the Control of Pollution Act 1974.