PART 2U.K.RULES IMPLEMENTING THE PUBLIC CONTRACTS DIRECTIVE

CHAPTER 2U.K.RULES ON PUBLIC CONTRACTS

SECTION 3U.K.Procedures

Open procedureU.K.

27.—(1) In open procedures, any interested economic operator may submit a tender in response to a contract notice.

(2) The minimum time limit for the receipt of tenders shall, subject to paragraphs (4) to (6), be 35 days from the date on which the contract notice is [F1submitted].

(3) The tender shall be accompanied by the information for qualitative selection that is requested by the contracting authority.

(4) Where contracting authorities have published a prior information notice F2..., the minimum time limit for the receipt of tenders as laid down in paragraph (2) may be shortened to 15 days, provided that both of the following conditions are fulfilled:—

(a)the prior information notice included all the information required [F3by regulation 48(2)] insofar as that information was available at the time the prior information notice was published;

(b)the prior information notice was [F4submitted] for publication between 35 days and 12 months before the date on which the contract notice was [F4submitted].

(5) Where a state of urgency duly substantiated by the contracting authority renders impracticable the time limit laid down in paragraph (2), it may fix a time limit which shall be not less than 15 days from the date on which the contract notice is [F5submitted].

(6) The contracting authority may reduce by 5 days the time limit for receipt of tenders set out in paragraph (2) where it accepts that tenders may be submitted by electronic means in accordance with regulation 22.