PART 2 E+WEnvironmental permits

CHAPTER 2E+WGrant of an environmental permit

Mobile plant operating on the site of another regulated facility: conflict of permit conditionsE+W

16.  If—

(a)an environmental permit (“permit A”) authorises the operation of mobile plant on the site of another regulated facility the operation of which is authorised under a separate environmental permit (“permit B”), and

(b)there is an inconsistency between the requirements imposed by permit A and those imposed by permit B,

the requirements imposed by permit B prevail.