SCHEDULE 1Activities, installations and mobile plant

PART 2Activities

CHAPTER 5Waste management

SECTION 5.6Temporary or underground storage of hazardous waste

Part A(1)

a

Temporary storage of hazardous waste with a total capacity exceeding 50 tonnes pending any of the activities listed in Sections 5.1, 5.2, 5.3 and paragraph (b) of this Section, except—

i

temporary storage, pending collection, on the site where the waste is generated, or

ii

activities falling within Section 5.2.

b

Underground storage of hazardous waste with a total capacity exceeding 50 tonnes.