SCHEDULE 5E+WEnvironmental permits

PART 1E+WGrant, variation, transfer and surrender of environmental permits

Making an applicationE+W

2.—(1) An application must—

(a)be made by the applicant on the form provided by the regulator, and

(b)include—

(i)such information as is specified on the form, and

(ii)any additional information required by the regulator.

(2) An application under regulation 13(1) for the grant of an environmental permit for a flood risk activity referred to in paragraph 3(1)(a) to (c) of Part 1 of Schedule 25 must be accompanied by—

(a)a fee of £50 for each flood risk activity to which the application relates, unless the regulator has made a charging scheme under section 41 of the 1995 Act M1, or

(b)where the regulator has made such a charging scheme, the fee prescribed under that scheme.

(3) Any other application must be accompanied by any fee prescribed in a charging scheme made by the regulator under section 41 of the 1995 Act or by the appropriate authority under regulation 66.

Marginal Citations

M1Section 41 was amended by paragraph 39 of Schedule 4 to the Flood and Water Management Act 2010 (c. 29), and by S.I. 2005/894, 1806 (W. 138), 2006/937, 2007/1711, 3106, 2008/3087, 2009/890, 3381, 2011/988, 1043, 2911, 2012/1659, 2788, 2013/755 (W. 90), 1821 and 2014/861.