SCHEDULEU.K.TRANSITIONAL ETC. PROVISION

PART 2U.K.PROCUREMENTS PENDING ETC. ON IP COMPLETION DAY

Saving for call-off procedures under certain framework agreementsU.K.

4.—(1) If the condition in sub-paragraph (2) is met, steady state amendments do not affect any procedure relating to the performance of a framework agreement, including the award of contracts based on such an agreement, under—

(a)regulation 33(4) to (11) of the Public Contracts Regulations 2015;

(b)regulation 51(4) to (6) of the Utilities Contracts Regulations 2016.

(2) The condition is that the framework agreement—

(a)was concluded before IP completion day and had neither expired nor been terminated before IP completion day; or

(b)was concluded after IP completion day in accordance with a procedure to which paragraph 3 applied.

Commencement Information

I1Sch. para. 4 in force at 31.12.2020 on IP completion day, see reg. 1(2)