The HyNet Carbon Dioxide Pipeline Order 2024

Operational and maintenance environmental management plan

19.—(1) The undertaker must, no later than three months prior to the planned completion of commissioning of the authorised development, submit to the relevant planning authorities the operational and maintenance environment management plan (or plans) which details the monitoring and management requirements of the authorised development, including post-construction monitoring.

(2) The operational and maintenance environment management plans submitted under sub-paragraph (1) must be in accordance with the outline operational and maintenance environment management plan, and developed having regard to the approved CEMP(s) and the LEMP(s).

(3) Operation of the authorised development must be implemented in accordance with the submitted operational and maintenance environment management plan(s).