PART 2WORKS PROVISIONS
Level Crossings
Construction of bridges14
1
Any bridge to be constructed under this Order for carrying a highway over or under a railway must be constructed in accordance with the plans and specifications approved by the highway authority but such approval is not to be unreasonably withheld.
2
If within 28 days of receiving an application for approval under paragraph (1) a highway authority fails to notify Network Rail of its decision or refuses approval without giving any grounds for its refusal that highway authority is deemed to have granted approval.
3
When making an application for approval under paragraph (1), Network Rail must notify the street authority of the effect of paragraph (2).