Search Legislation

The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015

 Help about what version

What Version

  • Latest available (Revised)
  • Original (As made)

Status:

This is the original version (as it was originally made). This item of legislation is currently only available in its original format.

PART 1Authorised development

1.  A nationally significant infrastructure project as defined in sections 14 and 15 of the 2008 Act(1) located in the Dogger Bank Zone comprising—

  • Project A offshore works

    • Work No. 1A

      (a)

      an offshore wind turbine generating station with a gross electrical output capacity of up to 1.2 gigawatts comprising up to 200 wind turbine generators each fixed to the seabed by monopole, multi-leg or gravity base type foundations situated within the area enclosed by the points whose co-ordinates are set out in Table 1A (the “array area”);

      Table 1A - Array area

      Point

      Latitude

      (decimal degrees)

      Longitude

      (decimal degrees)

      3155.117902.57524
      3255.118603.09890
      3355.106903.09409
      3455.090713.08744
      3555.074523.08080
      3655.058323.07416
      3755.042133.06752
      3855.025943.06090
      3955.009743.05427
      4054.994873.04820
      4154.978033.04132
      4254.977353.04104
      4354.961153.03444
      4454.954853.03187
      4554.955103.01393
      4654.955562.97851
      4754.955622.97450
      5054.960112.57690
      (b)

      up to 7 offshore platforms comprising the following—

      (i)

      up to 4 offshore collector platforms situated within the array area and fixed to the seabed by multi-leg or gravity base type foundations;

      (ii)

      1 offshore converter platform situated within the array area and fixed to the seabed by multi-leg or gravity base type foundations;

      (iii)

      up to 2 offshore accommodation or helicopter platforms situated within the array area and fixed to the seabed by multi-leg or gravity base type foundations,

      provided that any of the platforms comprised in Work No. 1A(b)(i) to (iii) may be co-joined to create a combined platform fixed to the seabed by multi-leg or gravity base type foundations;

      (c)

      up to 5 meteorological stations situated within the array area either fixed to the seabed by monopole, multi-leg or gravity base type foundations or utilising a floating support structure anchored to the seabed;

      (d)

      a network of cables for the transmission of electricity and electronic communications laid on or beneath the seabed (including cable crossings) between—

      (i)

      any of the wind turbine generators comprised in Work No. 1A(a);

      (ii)

      any of the wind turbine generators comprised in Work No. 1A(a) and any of the works comprised in Work No. 1A(c);

      (iii)

      any of the works comprised in Work No. 1A(b) and any of the works comprised in Work No. 1A(c); and

      (iv)

      the offshore converter platform referred to in Work No. 1A(b)(ii) or a combined platform referred to in Work No. 1A(b) and the export cable route in Work No. 2A; and

      (e)

      up to 10 vessel moorings situated within the array area consisting of a single floating buoy secured by chain and anchor anchored to the seabed.

2.  Associated development within the meaning of section 115(2) of the 2008 Act comprising—

  • Work No. 2A – up to 2 export cables for the transmission of HVDC electricity together with fibre-optic cables for the transmission of electronic communications laid on or beneath the seabed between Work No. 1A(b)(ii) or a combined platform referred to in Work No. 1A(b) and Work No. 3A (including cable crossings) and situated within the co-ordinates of the export cable corridor area specified in the offshore order limits and grid co-ordinates plan.

  • Project A onshore works

    In the Borough of Redcar and Cleveland—

    • Work No. 3A – up to 2 export cables for the transmission of HVDC electricity together with fibre-optic cables for the transmission of electronic communications laid underground between MLWS and MHWS connecting Work No. 2A with Work No. 4A;

    • Work No. 4A – up to 2 export cables for the transmission of HVDC electricity together with fibre-optic cables for the transmission of electronic communications laid underground between Work No. 3A at MHWS and Work No. 5A including the construction of a haul road and construction access;

    • Work No. 5A – landfall transition joint bays and trenchless installation drill launch pits together with associated landfill works, construction compound and up to 2 export cables for the transmission of HVDC electricity together with fibre-optic cables for the transmission of electric communications laid underground, in ducts if necessary, connecting Work No. 4A with Work No. 6A, including the construction of a haul road and construction access;

    • Work No. 6A – up to 2 export cables for the transmission of HVDC electricity together with fibre-optic cables for the transmission of electronic communications laid underground, in ducts if necessary, from Work No. 5A and running in a generally westerly direction for a distance of 7 kilometres to Work No. 7, including the construction of a haul road and construction access;

    • Work No. 8A – up to 3 export cables for the transmission of HVAC electricity together with fibre-optic cables for the transmission of electronic communications laid underground, in ducts if necessary, from 1 of the electrical converter substations comprised in Work No. 7 and running in a westerly direction for a distance of 2 kilometres to the connection bay within the National Grid substation connection works comprised in Work No. 9, including the construction of a haul road and construction access.

  • Project B offshore works

    • Work No. 1B

      (a)

      an offshore wind turbine generating station with a gross electrical output capacity of up to 1.2 gigawatts comprising up to 200 wind turbine generators each fixed to the seabed by monopole, multi-leg or gravity base type foundations situated within the area enclosed by the points whose co-ordinates are set out in Table 1B (the “array area”);

      Table 1B - Array area

      Point

      Latitude

      (decimal degrees)

      Longitude

      (decimal degrees)

      2555.124432.14572
      2655.130022.21780
      5154.970702.50189
      5254.960962.48529
      5654.838642.27783
      5754.838622.26336
      2455.011111.95454
      (b)

      up to 7 offshore platforms comprising the following—

      (i)

      up to 4 offshore collector platforms situated within the array area and fixed to the seabed by multi-leg or gravity base type foundations;

      (ii)

      1 offshore converter platform situated within the array area and fixed to the seabed by multi-leg or gravity base type foundations;

      (iii)

      up to 2 offshore accommodation or helicopter platforms situated within the array area and fixed to the seabed by multi-leg or gravity base type foundations,

      provided that any of the platforms comprised in Work No. 1B(b)(i) to (iii) may be co-joined to create a combined platform fixed to the seabed by multi-leg or gravity base type foundations;

      (c)

      up to 5 meteorological stations situated within the array area either fixed to the seabed by monopole, multi-leg or gravity base type foundations or utilising a floating support structure anchored to the seabed;

      (d)

      a network of cables for the transmission of electricity and electronic communications laid on or beneath the seabed (including cable crossings) between—

      (i)

      any of the wind turbine generators comprised in Work No. 1B(a);

      (ii)

      any of the wind turbine generators comprised in Work No. 1B(a) and any of the works comprised in Work No. 1B(c);

      (iii)

      any of the works comprised in Work No. 1B(b) and any of the works comprised in Work No. 1B(c);

      (iv)

      the offshore converter platform referred to in Work No. 1B(b)(ii) or a combined platform referred to in Work No. 1B(b) and the export cable route in Work No. 2B; and

      (e)

      up to 10 vessel moorings situated within the array area consisting of a single floating buoy secured by chain and anchor anchored to the seabed.

3.  Associated development within the meaning of section 115(2) of the 2008 Act comprising—

  • Work No. 2B – up to 2 export cables for the transmission of HVDC electricity together with fibre-optic cables for the transmission of electronic communications laid on or beneath the seabed between Work No. 1A(b)(ii) or a combined platform referred to in Work No. 1B(b) and Work No. 3B (including cable crossings) and situated within the co-ordinates of the export cable corridor area specified in the offshore order limits and grid co-ordinates plan.

  • Project B onshore works

    In the Borough of Redcar and Cleveland

    • Work No. 3B – up to 2 export cables for the transmission of HVDC electricity together with fibre-optic cables for the transmission of electronic communications laid underground between MLWS and MHWS connecting Work No. 2B with Work No. 4B;

    • Work No. 4B – up to 2 export cables for the transmission of HVDC electricity together with fibre-optic cables for the transmission of electronic communications laid underground between Work No. 3B at MHWS and Work No. 5B, including the construction of a haul road and construction access;

    • Work No. 5B – landfall transition joint bays and trenchless installation drill launch pits together with associated landfill works, construction compound and up to 2 export cables for the transmission of HVDC electricity together with fibre-optic cables for the transmission of electric communications laid underground, in ducts if necessary, connecting Work No. 4B with Work No. 6B, including the construction of a haul road and construction access;

    • Work No. 6B – up to 2 export cables for the transmission of HVDC electricity together with fibre-optic cables for the transmission of electronic communications laid underground, in ducts if necessary, from Work No. 5B and running in a generally westerly direction for a distance of 7 kilometres to Work No. 7, including the construction of a haul road and construction access;

    • Work No. 8B – up to 3 export cables for the transmission of HVAC electricity together with fibre-optic cables for the transmission of electronic communications, laid underground in ducts if necessary from 1 of the electrical converter substations comprised in Work No. 7 and running in a westerly direction for a distance of 2 kilometres to the connection bay within the National Grid substation connection works comprised in Work No. 9, including the construction of a haul road and construction access.

  • Shared works

    • Offshore

      • Work No. 2T – a temporary work area for vessels to carry out intrusive activities during construction, including vessels requiring anchor spreads, alongside the cable corridors.

    • Onshore

      • In the Borough of Redcar and Cleveland

        • Work No. 7 – up to 2 electrical converter substations and compounds for converting HVDC electricity carried by Work Nos. 6A and 6B to HVAC electricity (including landscaping and the construction of a temporary haul road) and—

          (a)

          up to 4 export cables for the transmission of HVDC electricity together with fibre-optic cables for the transmission of electronic communications laid underground, in ducts if necessary; and

          (b)

          up to 6 export cables for the transmission of HVAC electricity together with fibre-optic cables for the transmission of electronic communications laid underground, in ducts if necessary;

        • Work No. 7L – a screening landform to the south west of Work No. 7;

        • Work No. 8S – up to 6 export cables for the transmission of HVAC electricity together with fibre-optic cables for the transmission of electronic communications laid underground, in ducts if necessary, from the electrical converter substation comprised in Work No. 7 and running in a westerly direction for a distance of 575 metres to Work Nos. 8A and 8B, including the construction of a haul road and construction access;

        • Work No. 9 – National Grid substation connection works connecting Work Nos. 8A and 8B to the transmission network and comprising up to 6 export cables for the transmission of HVAC electricity together with fibre-optic cables for the transmission of electronic communications, including connection bays within the National Grid substation located above ground incorporating isolation switchgear, circuit bay equipment, overhead tubular connectors and switching and measuring equipment located above and below ground;

        • Work No. 10A – access road from Coast Road (A1085) to provide construction and maintenance access from the public highway to the development site and—

          (a)

          where shared with Work No. 6A, up to 2 export cables for the transmission of HVDC electricity together with fibre-optic cables for the transmission of electronic communications laid underground, in ducts if necessary;

          (b)

          where shared with Work No. 6B, up to 2 export cables for the transmission of HVDC electricity together with fibre-optic cables for the transmission of electronic communications laid underground, in ducts if necessary;

        • Work No. 10B – access road from Redcar Road to provide construction and maintenance access from the public highway to the development site and—

          (a)

          where shared with Work No. 6A, up to 2 export cables for the transmission of HVDC electricity together with fibre-optic cables for the transmission of electronic communications laid underground, in ducts if necessary;

          (b)

          where shared with Work No. 6B, up to 2 export cables for the transmission of HVDC electricity together with fibre-optic cables for the transmission of electronic communications laid underground, in ducts if necessary;

        • Work No. 10C – access from the A174 to provide construction and maintenance access from the public highway to the development site and—

          (a)

          where shared with Work No. 6A, up to 2 export cables for the transmission of HVDC electricity together with fibre-optic cables for the transmission of electronic communications laid underground, in ducts if necessary;

          (b)

          where shared with Work No. 6B, up to 2 export cables for the transmission of HVDC electricity together with fibre-optic cables for the transmission of electronic communications laid underground, in ducts if necessary;

        • Work No. 10D – access road from the A174 to provide construction and maintenance access from the public highway to the development site and

          (a)

          where shared with Work No. 6A, up to 2 export cables for the transmission of HVDC electricity together with fibre-optic cables for the transmission of electronic communications laid underground, in ducts if necessary;

          (b)

          where shared with Work No. 6B, up to 2 export cables for the transmission of HVDC electricity together with fibre-optic cables for the transmission of electronic communications laid underground, in ducts if necessary;

        • Work No. 10E– access road from Grewgrass Lane to provide construction and maintenance access from the public highway to the development site and

          (a)

          where shared with Work No. 6A, up to 2 export cables for the transmission of HVDC electricity together with fibre-optic cables for the transmission of electronic communications laid underground, in ducts if necessary;

          (b)

          where shared with Work No. 6B, up to 2 export cables for the transmission of HVDC electricity together with fibre-optic cables for the transmission of electronic communications laid underground, in ducts if necessary;

        • Work No. 10F – access road from Fishponds Road (B1269) to provide construction and maintenance access from the public highway to the development site and

          (a)

          where shared with Work No. 6A, up to 2 export cables for the transmission of HVDC electricity together with fibre-optic cables for the transmission of electronic communications laid underground, in ducts if necessary;

          (b)

          where shared with Work No. 6B, up to 2 export cables for the transmission of HVDC electricity together with fibre-optic cables for the transmission of electronic communications laid underground, in ducts if necessary;

        • Work No. 10G – access road from Fishponds Road (B1269) to provide construction and maintenance access from the public highway to the development site and—

          (a)

          where shared with Work No. 6A, up to 2 export cables for the transmission of HVDC electricity together with fibre-optic cables for the transmission of electronic communications laid underground, in ducts if necessary;

          (b)

          where shared with Work No. 6B, up to 2 export cables for the transmission of HVDC electricity together with fibre-optic cables for the transmission of electronic communications laid underground, in ducts if necessary;

        • Work No. 10H – access road from the intersection of A174 and A1042 to provide construction and maintenance access from the public highway to the development site and—

          (a)

          where shared with Work No. 6A, up to 2 export cables for the transmission of HVDC electricity together with fibre-optic cables for the transmission of electronic communications laid underground, in ducts if necessary;

          (b)

          where shared with Work No. 6B, up to 2 export cables for the transmission of HVDC electricity together with fibre-optic cables for the transmission of electronic communications laid underground, in ducts if necessary;

        • Work No. 10I – access road to provide construction and maintenance access from the public highway to the development site and—

          (a)

          where shared with Work No. 6A, up to 2 export cables for the transmission of HVDC electricity together with fibre-optic cables for the transmission of electronic communications laid underground, in ducts if necessary;

          (b)

          where shared with Work No. 6B, up to 2 export cables for the transmission of HVDC electricity together with fibre-optic cables for the transmission of electronic communications laid underground, in ducts if necessary;

        • Work No. 10J – access road to provide construction and maintenance access from the public highway to the development site and—

          (a)

          where shared with Work No. 8A, up to 3 export cables for the transmission of HVDC electricity together with fibre-optic cables for the transmission of electronic communications laid underground, in ducts if necessary;

          (b)

          where shared with Work No. 8B, up to 3 export cables for the transmission of HVDC electricity together with fibre-optic cables for the transmission of electronic communications laid underground, in ducts if necessary;

        • Work No. 10K – access road from the public highway High Street (B1380) to provide construction and maintenance access from the public highway to the development site.

        In connection with Work Nos. 3A, 4A, 5A, 6A, 7, 7L, 8A, 8S, 9 and 10A to 10K, the undertaker is granted development consent for the further associated development shown on the plans referred to in Requirement 19, or approved pursuant to the Requirements, including—

        (a)

        ramps, means of access and footpaths;

        (b)

        bunds, embankments, swales, landscaping and boundary treatments;

        (c)

        habitat creation;

        (d)

        boreholes;

        (e)

        jointing bays, manholes and other works associated with cable laying including trenchless installation works beneath watercourses roads and other obstructions;

        (f)

        water supply works, foul drainage provision and surface water management systems and culverting;

        (g)

        temporary structures to facilitate the crossing of watercourses including bailey bridges;

        (h)

        construction lay down areas and compounds and their restoration;

        (i)

        works to remove, reconstruct or alter the position of apparatus including mains, sewers, drains, cables and pipelines; and

        (j)

        such other works as may be necessary or expedient for the purposes of or in connection with the relevant part of the authorised project that fall within the scope of the works assessed by the environmental statement.

        In connection with Work Nos. 3B, 4B, 5B, 6B, 7, 7L, 8B, 8S, 9 and 10A to 10K, the undertaker is granted development consent for the further associated development shown on the plans referred to in Requirement 19, or approved pursuant to the Requirements, including—

        (a)

        ramps, means of access and footpaths;

        (b)

        bunds, embankments, swales, landscaping and boundary treatments;

        (c)

        habitat creation;

        (d)

        boreholes;

        (e)

        jointing bays, manholes and other works associated with cable laying including trenchless installation works beneath watercourses roads and other obstructions;

        (f)

        water supply works, foul drainage provision and surface water management systems and culverting;

        (g)

        temporary structures to facilitate the crossing of watercourses including bailey bridges;

        (h)

        construction lay down areas and compounds and their restoration;

        (i)

        works to remove, reconstruct or alter the position of apparatus including mains, sewers, drains, cables and pipelines; and

        (j)

        such other works as may be necessary or expedient for the purposes of or in connection with the relevant part of the authorised project that fall within the scope of the works assessed by the environmental statement.

(1)

Section 14 was amended by article 2(2) of S.I. 2012/1645.

Back to top

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources