Search Legislation

The East Anglia ONE North Offshore Wind Farm Order 2022

 Help about what version

What Version

 Help about advanced features

Advanced Features

Changes over time for: PART 1

 Help about opening options

Alternative versions:

Changes to legislation:

There are currently no known outstanding effects for the The East Anglia ONE North Offshore Wind Farm Order 2022, PART 1. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

PART 1E+W+SAuthorised development

1.  A nationally significant infrastructure project as defined in sections 14 and 15 of the 2008 Act which is located in the North Sea approximately 31 kilometres from the Suffolk coast, comprising—E+W+S

Work No. 1

(a)an offshore wind turbine generating station with a gross electrical output capacity of over 100 MW comprising up to 67 wind turbine generators each fixed to the seabed by one of five foundation types (namely monopile, jacket on suction caissons, jacket on piles, suction caisson or gravity base), fitted with rotating blades and situated within the area shown on the works plans and further comprising (b) to (c) below;

(b)up to one meteorological mast fixed to the seabed within the area shown on the works plans by one of five foundation types (namely monopile, jacket on suction caissons, jacket on piles, suction caisson or gravity base); and

(c)a network of subsea inter-array cables within the area shown on the works plans between the wind turbine generators and between the wind turbine generators and Work No. 3 including one or more cable crossings,

and associated development within the meaning of section 115(2) (development for which development consent may be granted) of the 2008 Act comprising—

Work No. 2 — up to one construction, operation and maintenance platform fixed to the seabed within the area shown on the works plans by one of four foundation types (namely monopile, jacket on suction caissons, jacket on piles or gravity base);

Work No. 3 — up to four offshore electrical platforms fixed to the seabed within the area shown on the works plans by one of four foundation types (namely monopile, jacket on suction caissons, jacket on piles or gravity base);

Work No. 4 — a network of subsea platform link cables within the area shown on the works plans between the offshore electrical platforms comprising Work No. 3 and between the construction, operation and maintenance platform comprising Work No. 2 and the offshore electrical platforms comprising Work No. 3 for the transmission of electricity and electronic communications including one or more cable crossings;

Work No. 5 — up to two subsea export cables between Work No. 3 and Work No. 6 within the area shown on the works plans including one or more cable crossings;

Work No. 6 — landfall connection works consisting of up to two export cables and up to two separate fibre optic cables laid underground within two cable ducts between Work No. 5 and Work No. 8 within the area shown on the works plans;

Work No. 7 — temporary construction consolidation sites and construction access;

Work No. 8 — the onshore transmission works at the landfall consisting of—

(a)up to two transition bays;

(b)up to two export cables and up to two separate fibre optic cables laid underground within two cable ducts from Work No. 6 to the transition bays;

(c)up to six electrical cables, up to two fibre optic cables and up to two distributed temperature sensing cables and up to ten cable ducts laid underground from the transition bays to Work No. 9;

(d)a temporary horizontal directional drilling compound;

(e)temporary construction consolidation sites;

(f)construction of a haul road; and

(g)access;

Work No. 9 — up to six electrical cables, up to two fibre optic cables and up to two distributed temperature sensing cables and up to ten cable ducts laid underground from Work No. 8 to Work No. 11 including construction of a haul road and access.

Work No. 10 — formation of a new access from Sizewell Gap including vegetation clearance to the south of Sizewell Gap;

Work No. 11 — up to six electrical cables, up to two fibre optic cables and up to two distributed temperature sensing cables and up to ten cable ducts laid underground from Work No. 9 to Work No. 12 together with a temporary trenchless technique compound, temporary construction consolidation sites, construction of a haul road and access.

Work No. 12 — up to six electrical cables, up to two fibre optic cables and up to two distributed temperature sensing cables and up to ten cable ducts laid underground from Work No. 11 to Work No. 13 including construction of a haul road and access.

Work No. 12A — temporary ecological mitigation works in accordance with the ecological management plan and associated access.

Work No. 13 — up to six electrical cables, up to two fibre optic cables and up to two distributed temperature sensing cables and up to ten cable ducts laid underground from Work No. 12 to Work No. 16 together with a temporary trenchless technique compound, construction of a haul road and access.

Work No. 14 — temporary ecological mitigation works in accordance with the ecological management plan and associated access.

Work No. 15 — formation of a new access at Sizewell Gap including vegetation clearance and construction of an access track to Work No. 13.

Work No. 16 — up to six electrical cables, up to two fibre optic cables and up to two distributed temperature sensing cables and up to ten cable ducts laid underground from Work No. 13 to Work No. 17 together with temporary construction consolidation sites, construction of a haul road and access.

Work No. 17 — up to six electrical cables, up to two fibre optic cables and up to two distributed temperature sensing cables and up to ten cable ducts laid underground from Work No. 16 to Work No. 18 and crossing Thorpe Road (B1353) together with the construction of a haul road and access.

Work No. 18 — up to six electrical cables, up to two fibre optic cables and up to two distributed temperature sensing cables and up to ten cable ducts laid underground from Work No. 17 to Work No. 19 together with temporary construction consolidation sites, construction of a haul road and access.

Work No. 19 — up to six electrical cables, up to two fibre optic cables and up to two distributed temperature sensing cables and up to ten cable ducts laid underground from Work No. 18 to Work No. 20 and crossing Aldeburgh Road (B1122) together with the construction of a haul road and access and the formation of a new access at Aldeburgh Road including vegetation clearance.

Work No. 20 — up to six electrical cables, up to two fibre optic cables and up to two distributed temperature sensing cables and up to ten cable ducts laid underground from Work No. 19 to Work No. 21 together with the construction of a haul road and access and the formation of a new access at Aldeburgh Road including vegetation clearance.

Work No. 21 — up to six electrical cables, up to two fibre optic cables and up to two distributed temperature sensing cables and up to ten cable ducts laid underground from Work No. 20 to Work No. 22 together with the construction of a haul road and access.

Work No. 22 — up to six electrical cables, up to two fibre optic cables and up to two distributed temperature sensing cables and up to ten cable ducts laid underground from Work No. 21 to Work No. 23 together with temporary construction consolidation sites, construction of a haul road and access.

Work No. 23 — up to six electrical cables, up to two fibre optic cables and up to two distributed temperature sensing cables and up to ten cable ducts laid underground from Work No. 22 to Work No. 26 together with the construction of a haul road and access and the formation of a new access at Snape Road (B1069) and a lay down area to the east of Snape Road.

Work No. 24 — permanent ecological mitigation works in accordance with the ecological management plan and associated access.

Work No. 25 — construction of bridleway to the west of Snape Road (B1069) connecting to the existing bridleway to the north including drainage works and fencing.

Work No. 26 — up to six electrical cables, up to two fibre optic cables and up to two distributed temperature sensing cables and up to ten cable ducts laid underground from Work No. 23 to Work No. 31 and crossing Snape Road (B1069) together with the construction of a haul road and access and the formation of a new access at Snape Road (B1069).

Work No. 27 — temporary construction consolidation sites and construction access;

Work No. 28 — ecological mitigation works in accordance with the ecological management plan and associated access.

Work No. 29 — permanent ecological mitigation works in accordance with the ecological management plan and associated access.

Work No. 30 — a new onshore substation at Grove Wood, Friston.

Work No. 31 — up to six electrical cables, up to two fibre optic cables and up to two distributed temperature sensing cables and up to ten cable ducts laid underground from Work No. 26 to Work No. 30 together with temporary construction consolidation sites, construction of a haul road, access and extension of permanent access comprised within Work No. 34.

Work No. 32 — a connection consisting of up to six electrical cables, up to two fibre optic cables and up to two distributed temperature sensing cables and up to ten cable ducts laid underground from Work No. 30 to Work No. 41 including a connection above ground and electrical engineering works within the national grid substation comprised within Work No. 41;

Work No. 33 — landscaping works including bunding and planting together with drainage works, sustainable drainage system ponds, surface water management systems, formation of footpaths and access.

Work No. 34 — formation of a new permanent access road from the B1121 north of Kiln Lane to the onshore substation and national grid substation including vegetation clearance on the eastern side of the road. Highway modifications and traffic management measures.

Work No. 35 — highway alterations to the junctions between the A1094 and the B1121 and the A1094 and the B1069 including widening of the highway and vegetation clearance.

Work No. 36 — highway alterations to the junction between the A12 and the A1094 including widening of the highway and vegetation clearance.

Work No. 37 — highway alterations comprising reinforcement of bridge together with temporary construction works area and formation of access from the A12,

and in connection with Work Nos. 1 to 6 and to the extent that they do not otherwise form part of any such work, further associated development comprising such other works as may be necessary or expedient for the purposes of or in connection with the relevant part of the authorised project and which fall within the scope of the work assessed by the environmental statement including—

(a)scour protection around the foundations of the offshore structures;

(b)cable protection measures such as rock placement and the placement of concrete mattresses and frond mattresses;

(c)dredging;

(d)the removal of material from the seabed required for the construction of Work Nos. 1 to 6 and the disposal of inert material of natural origin and dredged material within the Order limits produced during construction drilling and seabed preparation for the installation of the foundations of the offshore structures or during seabed preparation for cable laying;

and in connection with such Work Nos. 6 to 37 and to the extent that they do not otherwise form part of any such work, further associated development comprising such other works as may be necessary or expedient for the purposes of or in connection with the relevant part of the authorised project and which fall within the scope of the work assessed by the environmental statement, including—

(a)haul roads, ramps, and other vehicular and pedestrian means of access, including creation of new tracks and footpaths, and widening, upgrades, alterations and improvements of existing roads, tracks and footpaths;

(b)bunds, embankments, swales, landscaping and boundary treatments;

(c)habitat creation;

(d)spoil storage and associated control measures;

(e)jointing bays, link boxes, cable protection, joint protection, manholes, marker posts, tiles and tape, lighting and other works associated with laying cables and pulling cables through cable ducts;

(f)water supply works, foul drainage provision, surface water management systems, temporary drainage during installations of cables and culverting;

(g)works to alter the position of apparatus, including mains, sewers, drains and cables;

(h)works to alter the course of, or otherwise interfere with, non-navigable rivers, streams or watercourses;

(i)landscaping and other works to mitigate adverse effects of the construction, maintenance or operation of the authorised project;

(j)works for the benefit or protection of land affected by the authorised project;

(k)working sites in connection with the construction of the authorised project, construction lay down areas and compounds and storage compounds;

(l)works of restoration; and

(m)fencing or other means of enclosure.

Commencement Information

I1Sch. 1 Pt. 1 para. 1 in force at 22.4.2022, see art. 1(2)

2.  A nationally significant infrastructure project as defined in sections 14 and 16 (electric lines) of the 2008 Act comprising—E+W+S

Work No. 38 — up to three cable sealing end compounds, one of which may include circuit breakers, comprising an electrical compound with electrical equipment and overhead line gantries to allow the connection of Work No. 41 to the overhead lines comprised within Work No. 39 together with cables connecting the national grid substation to the cable sealing ends, extension of the permanent access comprised within Work No. 34 and works to the overhead line pylons.

Work No. 39 — replacement, upgrade and realignment works to the overhead line pylons in the vicinity of Work No. 38 together with up to one new additional overhead line pylon to the north west of the national grid substation comprised within Work No. 41.

Work No. 40 — temporary realignment works to the overhead line pylons in the vicinity of Work No. 38.

and associated development within the meaning of section 115(2) (development for which development consent may be granted) of the 2008 Act comprising—

Work No. 41 — a new national grid substation to the north west of Work No. 30 at Grove Wood, Friston and extension of permanent access comprised within Work No. 34.

Work No. 42 — temporary construction consolidation sites, access and extension of permanent access comprised within Work No. 34.

Work No. 43 — temporary working areas for the purposes of constructing Work Nos. 39 and 40 including access.

Work No. 34 — formation of a new permanent access road from the B1121 north of Kiln Lane to the onshore substation and national grid substation including vegetation clearance on the eastern side of the road, highway modifications and traffic management measures.

and in connection with such Work No. 34 and Work Nos. 38 to 43 and to the extent that they do not otherwise form part of any such work, further associated development comprising such other works as may be necessary or expedient for the purposes of or in connection with the relevant part of the authorised project and which fall within the scope of the work assessed by the environmental statement, including—

(a)haul roads, ramps, and other vehicular and pedestrian means of access, including creation of new tracks and footpaths, and widening, upgrades, alterations and improvements of existing roads, tracks and footpaths;

(b)bunds, embankments, swales, landscaping and boundary treatments;

(c)habitat creation;

(d)spoil storage and associated control measures;

(e)jointing bays, link boxes, cable protection, joint protection, manholes, marker posts, tiles and tape, lighting and other works associated with laying cables and pulling cables through cable ducts;

(f)water supply works, foul drainage provision, surface water management systems, temporary drainage during installations of cables and culverting;

(g)works to alter the position of apparatus, including mains, sewers, drains and cables;

(h)works to alter the course of, or otherwise interfere with, non-navigable rivers, streams or watercourses;

(i)landscaping and other works to mitigate adverse effects of the construction, maintenance or operation of the authorised project;

(j)works for the benefit or protection of land affected by the authorised project;

(k)working sites in connection with the construction of the authorised project, construction lay down areas and compounds and storage compounds;

(l)works of restoration; and

(m)fencing or other means of enclosure.

Commencement Information

I2Sch. 1 Pt. 1 para. 2 in force at 22.4.2022, see art. 1(2)

3.  The grid coordinates for that part of the authorised project which is seaward of MHWS are specified below and more particularly shown on the Order limits boundary coordinates plan (offshore)—E+W+S

PointLatitudeLongitude
152° 21 40.240N02° 18 57.351E
252° 22 49.082N02° 18 20.131E
352° 25 41.851N02° 18 38.726E
452° 26 07.817N02° 19 55.691E
552° 25 47.948N02° 34 14.117E
652° 20 33.278N02° 34 13.789E
752° 20 19.052N02° 28 56.310E
852° 18 11.924N02° 20 49.771E
952° 21 07.976N02° 19 14.783E
1052° 19 34.060N02° 11 21.980E
1152° 19 10.459N02° 10 57.491E
1252° 19 10.410N02° 08 40.019E
1352° 17 42.613N02° 08 31.830E
1452° 18 44.262N02° 06 49.319E
1552° 18 39.650N01° 57 24.848E
1652° 17 25.858N01° 54 09.969E
1752° 17 24.663N01° 52 03.374E
1852° 17 24.629N01° 52 03.277E
1952° 15 14.373N01° 45 57.606E
2052° 14 29.510N01° 45 06.050E
2152° 10 51.365N01° 42 32.460E
2252° 09 56.713N01° 39 52.443E
2352° 09 53.117N01° 38 40.253E
2452° 10 06.702N01° 37 38.597E
2552° 10 44.466N01° 37 04.551E
2652° 11 01.504N01° 37 17.750E
2752° 11 02.378N01° 37 15.833E
2852° 11 11.451N01° 37 20.545E
2952° 11 22.030N01° 37 22.233E
3052° 11 30.678N01° 37 21.417E
3152° 11 31.210N01° 37 24.534E
3252° 11 33.421N01° 37 24.505E
3352° 11 53.663N01° 37 50.246E
3452° 12 26.106N01° 40 17.584E
3552° 13 37.194N01° 41 04.014E
3652° 15 54.943N01° 45 03.442E
3752° 18 25.193N01° 52 05.276E
3852° 20 19.496N01° 56 37.327E
3952° 20 25.400N02° 08 48.429E
4052° 20 02.196N02° 08 47.461E
4152° 20 02.239N02° 10 44.070E

Commencement Information

I3Sch. 1 Pt. 1 para. 3 in force at 22.4.2022, see art. 1(2)

4.  Notwithstanding the grid coordinates specified at paragraph 3 and notwithstanding anything to the contrary shown on the work plans referred to in this Part, no part of Work No. 1(a) or Work No. 1(b) may be carried out if it falls within 8 kilometres of the boundary of the Outer Thames Estuary Special Protection Area.E+W+S

Commencement Information

I4Sch. 1 Pt. 1 para. 4 in force at 22.4.2022, see art. 1(2)

Back to top

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources