The Public Contracts Regulations 2015

 Help about what version

Pa Fersiwn

 Help about advanced features

Nodweddion Uwch

Changes over time for: Cross Heading: SECTION 6

 Help about opening options

Changes to legislation:

The Public Contracts Regulations 2015, Cross Heading: SECTION 6 is up to date with all changes known to be in force on or before 29 May 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.

View outstanding changes

Changes and effects yet to be applied to Part 2 Chapter 2 Crossheading Contract-performance:

Changes and effects yet to be applied to the whole Instrument associated Parts and Chapters:

Whole provisions yet to be inserted into this Instrument (including any effects on those provisions):

  • reg. 6(15A) words omitted by S.I. 2023/506 reg. 2(3)(a) (This amendment not applied to legislation.gov.uk. S.I. 2023/506 revoked before coming into force by The Public Procurement (International Trade Agreements) (Amendment) (Wales) (No. 2) Regulations 2023 (S.I. 2023/567), regs. 1(2), 6)
  • reg. 10(1)(d)(i)(aa) words substituted by S.I. 2019/560 reg. 5(9)(a)(i) (This amendment not applied to legislation.gov.uk. Affecting Regulations revoked (20.11.2020) by S.I. 2020/1319, regs. 1(3), 2(a))
  • reg. 10(1)(d)(i)(bb) words substituted by S.I. 2019/560 reg. 5(9)(a)(ii) (This amendment not applied to legislation.gov.uk. Affecting Regulations revoked (20.11.2020) by S.I. 2020/1319, regs. 1(3), 2(a))
  • reg. 18(4) words omitted by S.I. 2023/506 reg. 2(4) (This amendment not applied to legislation.gov.uk. S.I. 2023/506 revoked before coming into force by The Public Procurement (International Trade Agreements) (Amendment) (Wales) (No. 2) Regulations 2023 (S.I. 2023/567), regs. 1(2), 6)

SECTION 6U.K.Contract Performance

Conditions for performance of contractsU.K.

70.—(1) Contracting authorities may lay down special conditions relating to the performance of a contract, provided that they are—

(a)linked to the subject-matter of the contract within the meaning of regulation 67(5), and

(b)indicated in the call for competition or in the procurement documents.

(2) Those conditions may include economic, innovation-related, environmental, social or employment-related considerations.

SubcontractingU.K.
Giving information to contracting authorities

71.—(1) In the procurement documents, the contracting authority may ask the tenderer to indicate in its tender any share of the contract that it may intend to subcontract to third parties and any proposed subcontractors.

(2) Paragraph (1) is without prejudice to the main contractor's liability.

(3) In the case of works contracts and in respect of services to be provided at a facility under the direct oversight of the contracting authority, after the award of the contract and at the latest when the performance of the contract commences, the contracting authority shall require the main contractor to notify to the contracting authority the name, contact details and legal representatives of its subcontractors, involved in such works or services, in so far as known at the time.

(4) The contracting authority shall require the main contractor to notify the contracting authority of—

(a)any changes to the information notified under paragraph (3) during the course of the contract; and

(b)the name, contact details and legal representatives of any new subcontractors which the main contractor subsequently involves in such works or services.

(5) Where necessary for the purposes of paragraph (8), the required information shall be accompanied by [F1SPDs] in respect of the subcontractors.

(6) Paragraphs (3) and (4) do not apply to suppliers.

(7) Contracting authorities may extend the obligations provided for in paragraphs (3) and (4) to, for example—

(a)supply contracts, services contracts (other than those concerning services to be provided at the facilities under the direct oversight of the contracting authority) or suppliers involved in works or services contracts;

(b)subcontractors of the main contractor's subcontractors or subcontractors further down the subcontracting chain.

Excluding subcontractors

(8) Contracting authorities may, in accordance with regulations 59, 60 and 61, verify whether there are grounds for exclusion of subcontractors under regulation 57.

(9) In such cases, the contracting authority—

(a)shall require that the economic operator replaces a subcontractor in respect of which the verification has shown that there are compulsory grounds for exclusion; and

(b)may require that the economic operator replaces a subcontractor in respect of which the verification has shown that there are non-compulsory grounds for exclusion.

Textual Amendments

Modification of contracts during their termU.K.

72.—(1) Contracts and framework agreements may be modified without a new procurement procedure in accordance with this Part in any of the following cases:—

(a)where the modifications, irrespective of their monetary value, have been provided for in the initial procurement documents in clear, precise and unequivocal review clauses, which may include price revision clauses or options, provided that such clauses—

(i)state the scope and nature of possible modifications or options as well as the conditions under which they may be used, and

(ii)do not provide for modifications or options that would alter the overall nature of the contract or the framework agreement;

(b)for additional works, services or supplies by the original contractor that have become necessary and were not included in the initial procurement, where a change of contractor—

(i)cannot be made for economic or technical reasons such as requirements of interchangeability or interoperability with existing equipment, services or installations procured under the initial procurement, [F2and]

(ii)would cause significant inconvenience or substantial duplication of costs for the contracting authority,

provided that any increase in price does not exceed 50% of the value of the original contract;

(c)where all of the following conditions are fulfilled:—

(i)the need for modification has been brought about by circumstances which a diligent contracting authority could not have foreseen;

(ii)the modification does not alter the overall nature of the contract;

(iii)any increase in price does not exceed 50% of the value of the original contract or framework agreement.

(d)where a new contractor replaces the one to which the contracting authority had initially awarded the contract as a consequence of—

(i)an unequivocal review clause or option in conformity with sub-paragraph (a), or

(ii)universal or partial succession into the position of the initial contractor, following corporate restructuring, including takeover, merger, acquisition or insolvency, of another economic operator that fulfils the criteria for qualitative selection initially established, provided that this does not entail other substantial modifications to the contract and is not aimed at circumventing the application of this Part;

(e)where the modifications, irrespective of their value, are not substantial within the meaning of paragraph (8); or

(f)where paragraph (5) applies.

(2) Where several successive modifications are made:—

(a)the limitations imposed by the proviso at the end of paragraph (1)(b) and by paragraph (c)(iii) shall apply to the value of each modification; and

(b)such successive modifications shall not be aimed at circumventing this Part.

(3) Contracting authorities which have modified a contract in either of the cases described in paragraph (1)(b) and (c) shall [F3submit] a notice to that effect, in accordance with regulation 51, for publication.

(4) Such a notice shall contain the information set out in part G of Annex 5 to the Public Contracts Directive[F4, but as if—

(a)paragraph 9 (financing by EU funds) were omitted;

(b)in paragraph 11, “in the Official Journal of the European Union” read “on the UK e-notification service (within the meaning of the Public Contracts Regulations 2015)”; and

(c)in paragraph 12, “date of dispatch” were a reference to the date on which the notice is submitted to the UK e-notification service for the purposes of these Regulations].

(5) This paragraph applies where the value of the modification is below both of the following values:—

(a)the relevant threshold mentioned in regulation 5, and

(b)10% of the initial contract value for service and supply contracts and 15% of the initial contract value for works contracts,

provided that the modification does not alter the overall nature of the contract or framework agreement.

(6) For the purposes of paragraph (5), where several successive modifications are made, the value shall be the net cumulative value of the successive modifications.

(7) For the purpose of the calculation of—

(a)the price mentioned in paragraph (1)(b) and (c), and

(b)the values mentioned in paragraph (5)(b),

the updated figure shall be the reference figure when the contract includes an indexation clause.

(8) A modification of a contract or a framework agreement during its term shall be considered substantial for the purposes of paragraph (1)(e) where one or more of the following conditions is met:—

(a)the modification renders the contract or the framework agreement materially different in character from the one initially concluded;

(b)the modification introduces conditions which, had they been part of the initial procurement procedure, would have—

(i)allowed for the admission of other candidates than those initially selected,

(ii)allowed for the acceptance of a tender other than that originally accepted, or

(iii)attracted additional participants in the procurement procedure;

(c)the modification changes the economic balance of the contract or the framework agreement in favour of the contractor in a manner which was not provided for in the initial contract or framework agreement;

(d)the modification extends the scope of the contract or framework agreement considerably;

(e)a new contractor replaces the one to which the contracting authority had initially awarded the contract in cases other than those provided for in paragraph (1)(d).

(9) A new procurement procedure in accordance with this Part shall be required for modifications of the provisions of a public contract or a framework agreement during its term other than those provided for in this regulation.

Termination of contractsU.K.

73.—(1) Contracting authorities shall ensure that every public contract which they award contains provisions enabling the contracting authority to terminate the contract where—

(a)the contract has been subject to a substantial modification which would have required a new procurement procedure in accordance with regulation 72(9); [F5or]

(b)the contractor has, at the time of contract award, been in one of the situations referred to in regulation 57(1), including as a result of the application of regulation 57(2), and should therefore have been excluded from the procurement procedureF6...

F7(c). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

(2) Those provisions may address the basis on which the power is to be exercisable in those circumstances, for example by providing for notice of termination to be given and by addressing consequential matters that will or might arise from the termination.

(3) To the extent that a public contract does not contain provisions enabling the contracting authority to terminate the contract on any of the grounds mentioned in paragraph (1), a power for the contracting authority to do so on giving reasonable notice to the contractor shall be an implied term of that contract.

Yn ôl i’r brig

Options/Help

Print Options

You have chosen to open yr Offeryn Cyfan

Yr Offeryn Cyfan you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

Y Rhestrau you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.

Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.

Close

Gweler y wybodaeth ychwanegol ochr yn ochr â’r cynnwys

Rhychwant ddaearyddol: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Dangos Llinell Amser Newidiadau: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Memorandwm Esboniadol

Mae Memoranda Esboniadol yn nodi datganiad byr o ddiben Offeryn Statudol ac yn rhoi gwybodaeth am ei amcan polisi a goblygiadau polisi. Maent yn ceisio gwneud yr Offeryn Statudol yn hygyrch i ddarllenwyr nad oes ganddynt gymhwyster cyfreithiol, ac maent yn cyd-fynd ag unrhyw Offeryn Statudol neu Offeryn Statudol Drafft a gyflwynwyd ger bron y Senedd o Fehefin 2004 ymlaen.

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Llinell Amser Newidiadau

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel gwnaed fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill