This is a draft item of legislation. This draft has since been made as a UK Statutory Instrument: The Nuclear Regulated Asset Base Model (Revenue Collection) Regulations 2023 No. 254
5.—(1) The revenue collection counterparty must, in respect of every quarterly obligation period, determine an interim levy rate which is to apply for that period.
(2) The revenue collection counterparty must determine the interim levy rate for a quarterly obligation period at least 30 days before the commencement of that quarterly obligation period.
(3) Where the revenue collection counterparty has determined an interim levy rate for a quarterly obligation period it must—
(a)as soon as reasonably practicable, publish a notice setting out that rate and issue that notice to every electricity supplier who has a BM Unit registered as at the day before the date of publication of the notice, and
(b)issue that notice to every electricity supplier who has a BM Unit that becomes registered on or after the date of publication of the notice and by the last day of the quarterly obligation period to which that rate applies, as soon as reasonably practicable after the BM Unit is registered.
(4) Subject to paragraph (5), the interim levy rate for a quarterly obligation period is to be determined as the amount given by—
where—
EOC is the estimated quarterly obligation period payment cost, determined in accordance with regulation 6(1);
EOI is the estimated quarterly obligation period income, determined in accordance with regulation 6(2); and
EOS is the estimated quarterly obligation period electricity supply, estimated in accordance with regulation 6(4).
(5) Where the amount given by the calculation in paragraph (4) in relation to a quarterly obligation period is less than zero, the interim levy rate must be determined as zero for that period.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Draft Explanatory Memorandum sets out a brief statement of the purpose of a Draft Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Draft Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: