PART 3Determining obligations and minimum requirements

Application of this Part

5.—(1) This Part applies in relation to a participant in respect of the supply of electricity.

(2) This Part also applies in relation to a participant in respect of the supply of gas in the same way as it applies to a participant in respect of the supply of electricity, but as if for each reference to “electricity” there were substituted “gas”.

Determining a participant’s obligations and minimum requirements

6.—(1) The Administrator must determine for each participant in relation to an ECO4A phase the participant’s home-heating cost reduction obligation for that ECO4A phase.

(2) The Administrator must also determine for each participant in relation to an ECO4A phase the participant’s low-income minimum requirement for that ECO4A phase.

(3) For the purposes of paragraphs (1) and (2), the Administrator must—

(a)in the case of a participant who is not a member of a group at the end of the qualification year for the ECO4A phase, make the determination in accordance with article 7;

(b)in the case of a participant who is a member of a group at the end of the qualification year for the ECO4A phase, make the determination in accordance with article 8.

(4) Anything determined by the Administrator under article 5(5) of the 2022 Order in relation to a participant is to be treated for the purposes of articles 7 and 8 of this Order as if it were notified by that participant.

(5) The Administrator must notify a participant of its home-heating cost reduction obligation and low-income minimum requirement in writing—

(a)for phase A, within the period of 6 weeks beginning with the commencement date;

(b)for phases B and C, on or before the 7th March prior to the commencement of the ECO4A phase.

Determining obligations and minimum requirements for participants who are not members of a group

7.—(1) Where a participant is not a member of a group at the end of the qualification year for the ECO4A phase—

(a)if the participant has notified the Administrator under article 5(2) of the 2022 Order of an amount of electricity supplied in the qualification year for the equivalent ECO4 phase which is less than the qualifying supply, the Administrator must determine the participant’s home-heating cost reduction obligation and low-income minimum requirement for the ECO4A phase to be zero;

(b)otherwise—

(i)the Administrator must determine the participant’s home-heating cost reduction obligation for the ECO4A phase in accordance with the following formula—

D x Tp / T; and

(ii)the Administrator must determine the participant’s low-income minimum requirement for the ECO4A phase in accordance with the following formula—

Hp x 0.2.

(2) In paragraph (1)(b)(i)—

(a)“D” is—

(i)for phase A, £3,640,000;

(ii)for phase B, £12,179,500;

(iii)for phase C, £12,179,500;

(b)“Tp” is the amount of electricity supplied in the qualification year for the equivalent ECO4 phase by the participant as determined under article 9(2) of the 2022 Order;

(c)“T” is the total amount of electricity supplied in the qualification year for the equivalent ECO4 phase by all participants as determined under article 9(4) of the 2022 Order.

(3) In paragraph (1)(b)(ii), “Hp” is the participant’s home-heating cost reduction obligation for the ECO4A phase.

Determining obligations and minimum requirements for participants who are members of a group

8.—(1) Where a participant is a member of a group at the end of the qualification year for the ECO4A phase—

(a)if the participant has notified the Administrator under article 5(3) of the 2022 Order of an amount of electricity supplied by the group in the qualification year for the equivalent ECO4 phase which is less than the qualifying supply, the Administrator must determine the participant’s home-heating cost reduction obligation and low-income minimum requirement for the ECO4A phase to be zero;

(b)otherwise—

(i)the Administrator must determine the participant’s home-heating cost reduction obligation for the ECO4A phase in accordance with the following formula—

(D x Tg / T) x (Np / Ng); and

(ii)the Administrator must determine the participant’s low-income minimum requirement for the ECO4A phase in accordance with the following formula—

Hp x 0.2.

(2) In paragraph (1)(b)(i)—

(a)D” and “T” have the same meaning as in article 7;

(b)“Tg” is the amount of electricity supplied in the qualification year for the equivalent ECO4 phase by the group of which the participant is a member as determined under article 9(3) of the 2022 Order;

(c)“Np” is the amount of electricity notified by the participant under article 5(2) of the 2022 Order as supplied in the qualification year for the equivalent ECO4 phase by the participant;

(d)“Ng” is the amount of electricity notified by the participant under article 5(3) of the 2022 Order as supplied in the qualification year for the equivalent ECO4 phase by the group of which the participant is a member.

(3) In paragraph (1)(b)(ii), “Hp” is the participant’s home-heating cost reduction obligation for the ECO4A phase.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Draft Explanatory Memorandum

Draft Explanatory Memorandum sets out a brief statement of the purpose of a Draft Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Draft Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Impact Assessments

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources