PART 3 Acquisition and Possession of Land
PART 4 Operation of Tram System
SCHEDULES
MODIFICATION OF COMPENSATION AND COMPULSORY PURCHASE ENACTMENTS FOR CREATION OF NEW RIGHTS
3.(1) The 1965 Act shall have effect with the modifications...
4.For section 7 of the 1965 Act (measure of compensation)...
6.The following provisions of the 1965 Act (which state the...
8.Section 20 of the 1965 Act (protection for interests of...
9.Section 22 of the 1965 Act (protection of acquiring authority’s...
FOR PROTECTION OF ELECTRICITY, GAS, WATER AND SEWERAGE UNDERTAKERS
8.Paragraphs 9 to 12 apply where— (a) Merseytravel requires the...
9.Merseytravel shall, if it is practicable to do so, afford...
10.The obligation imposed upon the specified undertaker by paragraph 9...
11.Any alternative apparatus to be constructed by the specified undertaker...
12.The specified undertaker shall, after the manner of construction and...
Removal of apparatus and construction of alternative apparatus by Merseytravel
Retained apparatus: protection and plan approval
20.Not less than 56 days before commencing to construct or...
22.Merseytravel shall not commence the construction or renewal of any...
23.Any approval of the specified undertaker required under paragraph 22—...
25.A specified work shall be constructed (and in the case...
27.Nothing in paragraph 20 or 26 shall preclude Merseytravel from...
28.Merseytravel shall not be required to comply with paragraph 20...
29.Nothing in paragraph 28 shall entitle Merseytravel to carry out...