Search Legislation

The Utilities Contracts Regulations 2006 (revoked)

Changes over time for: Section 17

 Help about opening options

Version Superseded: 28/06/2013

Status:

Point in time view as at 31/01/2006. This version of this provision has been superseded. Help about Status

Close

Status

You are viewing this legislation item as it stood at a particular point in time. A later version of this or provision, including subsequent changes and effects, supersedes this version.

Note the term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section.

Changes to legislation:

There are currently no known outstanding effects for the The Utilities Contracts Regulations 2006 (revoked), Section 17. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Award without a call for competitionE+W+N.I.

This section has no associated Explanatory Memorandum

17.—(1) A utility may seek offers in relation to a proposed contract without a call for competition in the following circumstances—

(a)in the absence of tenders, suitable tenders or applications in response to a procedure with a call for competition but only if the original terms of the proposed contract offered in the discontinued procedure have not been substantially altered;

(b)when the contract is to be awarded purely for the purposes of research, experiment, study or development but not where it has the purpose of securing profit or of recovering research and development costs and insofar as its award will not prejudice the competitive award of subsequent contracts which are, in particular, for the same purposes;

(c)when, for technical or artistic reasons, or for reasons connected with the protection of exclusive rights, the contract may only be performed by a particular economic operator;

(d)when (but only if it is strictly necessary) for reasons of extreme urgency brought about by events unforeseeable by the utility the time limits specified in regulation 22(2) to (11) cannot be met;

(e)when the contract to be awarded is a supply contract and the goods to be purchased or hired under the contract are required by the utility as a partial replacement for, or in addition to, existing goods or an installation and when to obtain the goods from a supplier other than the supplier which supplied the existing goods or the installation would oblige the utility to acquire goods having different technical characteristics which would result in—

(i)incompatibility between the existing goods or the installation and the goods to be purchased or hired under the contract; or

(ii)disproportionate technical difficulties in the operation and maintenance of the goods or the installation;

(f)when a utility wants an economic operator which has entered into a works contract or a services contract with that utility to carry out additional work or works or provide additional services which were not included in the project initially considered or in the original works contract or services contract but which through unforeseen circumstances have become necessary, and such work, works or services—

(i)cannot for technical or economic reasons be carried out or provided separately from those under the original contract without major inconvenience to the utility; or

(ii)can be carried out or provided separately from those under the original contract but are strictly necessary to the later stages of the performance of that contract;

(g)subject to paragraph (2), when the utility wants an economic operator which has entered into a works contract with that utility following a call for competition which satisfies the requirement of regulation 16(1) to carry out new work or works which are a repetition of the work or works carried out under the original contract and which are in accordance with the project for the purpose of which the first contract was entered into;

(h)in respect of a supply contract for the purchase or hire of goods quoted and purchased on a commodity market;

(i)when the contract to be awarded is to be awarded under a framework agreement which has been concluded in accordance with these Regulations and to which the provisions of regulation 18 apply;

(j)when the contract to be awarded is a supply contract, to take advantage of a particularly advantageous bargain available for a very short period of time at a price considerably lower than normal market prices;

(k)when the contract to be awarded is a supply contract, to take advantage of particularly advantageous conditions for the purchase of goods in a closing down sale or in a sale brought about because a supplier is subject to a procedure referred to in regulation 26(5)(a), (b) and (c); and

(l)in the case of services contracts, when the rules of a design contest require the contract to be awarded to the successful contestant or to one of the successful contestants, provided that all successful contestants are invited to negotiate the contract.

(2) A utility shall not seek offers without a call for competition in accordance with paragraph (1)(g) unless—

(a)the original contract was awarded after a call for competition;

(b)when the utility invited contractors to tender for or negotiate the contract it gave notice that a works contract for new work or works which would be a repetition of the work or works carried out under the original contract may be awarded without a call for competition in accordance with paragraph (1)(g); and

(c)in determining the estimated value of the original contract for the purposes of regulation 11 the utility took into account the value of the consideration which it expected to be payable for the new works.

Back to top

Options/Help

Print Options

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources