Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
24.—[F2(1) Where the appropriate authority has given EIA consent in respect of a regulated activity, the regulator may proceed to deal with the application and take its regulatory decision in accordance with the relevant legislation.]
[F3(1A) When the regulator proceeds to deal with the application and take its regulatory decision in accordance with paragraph (1), the regulator must have regard to the written confirmation of the EIA consent decision and in particular to any conditions, including any mitigating or monitoring measures, attached to that decision pursuant to regulation 22(1)(c) to (e).
(1B) Where the regulator decides to grant regulatory approval, the regulator must incorporate in the regulatory decision—
(a)the conclusion reached by the appropriate authority in accordance with regulation 21A(2);
(b)any conditions, including any mitigating or monitoring measures, attached to the regulatory decision; and
(c)a statement including—
(i)the main reasons and considerations on which the regulatory decision is based including, if relevant, information about the participation of the public; and
(ii)a summary of the results of the consultations undertaken, and information gathered, in respect of the application and how those results (in particular, in circumstances where regulation 18 applies, the comments received from an EEA State pursuant to consultation under that regulation) have been incorporated or otherwise addressed.
(1C) Where the regulator decides to refuse regulatory approval, the regulator must state the main reasons for the refusal.
(1D) The regulator must be satisfied that the information incorporated in the EIA consent decision, under regulation 23(2), is up to date at the time that the regulatory decision is taken, but that information must be taken to be up to date if, in the opinion of the regulator, it addresses the significant effects that are likely to arise as a result of the project proposed.
(1E) The regulatory decision must be taken within a period of time which—
(a)is reasonable, taking into account the nature and complexity of the regulated activity; and
(b)begins with the date on which the EIA consent decision is published.]
(2) Where the appropriate authority has refused EIA consent in respect of a regulated activity, the regulator may not grant a regulatory approval for that regulated activity and must treat the application for that regulated activity as having been withdrawn.]
Textual Amendments
F1Regulations revoked (S.) (16.5.2017) by The Marine Works (Environmental Impact Assessment) (Scotland) Regulations 2017 (S.S.I. 2017/115), reg. 42(a) (with regs. 1(2), 40, 41)
F2Reg. 24(1) substituted (16.5.2017) by The Marine Works (Environmental Impact Assessment) (Amendment) Regulations 2017 (S.I. 2017/588), regs. 1(1), 24(2) (with reg. 34)
F3Reg. 24(1A)-(1E) inserted (16.5.2017) by The Marine Works (Environmental Impact Assessment) (Amendment) Regulations 2017 (S.I. 2017/588), regs. 1(1), 24(3) (with reg. 34)
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: