PART 1Interpretation and application: general

Interpretation

1.  In this Schedule, “background quantity” means, in relation to the release of a substance resulting from an activity, such quantity of that substance as is present in—

(a)water supplied to the site where the activity is carried on;

(b)water abstracted for use in the activity; and

(c)precipitation onto the site on which the activity is carried on.

Activities falling within more than one Part description

2.—(1) Where, in Part 2 of this Schedule, an activity falls within a description in Part A(1) and a description in Part A(2) that activity must be regarded as falling only within that description which fits it most aptly.

(2) Where, in Part 2 of this Schedule, an activity falls within a description in Part A(1) and a description in Part B (other than a description in Section 7) that activity must be regarded as falling only within the description in Part A(1).

(3) Where, in Part 2 of this Schedule, an activity falls within a description in Part A(2) and a description in Part B (other than a description in Section 7) that activity must be regarded as falling only within the description in Part A(2).

(4) If, immediately before the coming into force of these Regulations, an installation where a Part A(2) activity and a waste operation were carried out was a Part A(1) installation by virtue of paragraph 17 of Part 3 of Schedule 1 to the 2000 Regulations, that installation carries on a Part A(1) activity for the purposes of these Regulations.

Application of activities falling within Sections 1.1 to 6.9 of Part 2

3.  An activity must not be taken to be an activity falling within Sections 1.1 to 6.9 of Part 2 if it is—

(a)carried on in a working museum to demonstrate an industrial activity of historic interest;

(b)carried on for educational purposes in a school as defined in section 4(1) of the Education Act 1996(1);

(c)carried on at an installation or mobile plant solely used for research, development and testing of new products and processes;

(d)the running on or within an aircraft, hovercraft, mechanically propelled road vehicle, railway locomotive or ship or other vessel of an engine which propels or provides electricity for it;

(e)the running of an engine in order to test it before it is installed or in the course of its development; or

(f)carried on as a domestic activity in connection with a private dwelling.

Capacity: Part A(1) and A(2) descriptions

4.—(1) This paragraph applies for the purpose of determining whether an activity carried on in a stationary technical unit falls within a description in Part A(1) or Part A(2) of Part 2 of this Schedule which refers to capacity, other than design holding capacity.

(2) Where a person carries out several activities falling within the same description in Part A(1) or Part A(2) in different parts of the same stationary technical unit or in different stationary technical units on the same site, the capacities of each part or unit, as the case may be, must be added together and the total capacity must be attributed to each part or unit for the purpose of determining whether the activity carried on in each part or unit falls within a description in Part A(1) or Part A(2).

(3) For the purpose of sub-paragraph (2), no account must be taken of capacity when determining whether activities fall within the same description.

(4) Where an activity falls within a description in Part A(1) or Part A(2) by virtue of this paragraph it must not be taken to be an activity falling within a description in Part B (other than a description in Section 7).

Operation below thresholds: effect on the installation

5.  Where an operator is authorised by an environmental permit to carry out Part A(1) activities, Part A(2) activities or Part B activities which are described in Part 2 of this Schedule by reference to a threshold (whether in terms of capacity or otherwise) at an installation, the installation does not cease to be a Part A(1) installation, a Part A(2) installation, or a Part B installation, as the case may be, by virtue of the installation being operated below the relevant threshold unless the permit ceases to have effect in accordance with these Regulations.

Application of Part B activities: releases into the air

6.—(1) Subject to sub-paragraph (2), an activity must not be taken to be a Part B activity within Part 2 of this Schedule if it cannot result in the release into the air of a substance listed in sub-paragraph (3) or there is no likelihood that it will result in the release into the air of any such substance except in a quantity which is so trivial that it is incapable of causing pollution or its capacity to cause pollution is insignificant.

(2) Sub-paragraph (1) does not apply to—

(a)an SED activity; or

(b)an activity which may give rise to an offensive smell noticeable outside the site where the activity is carried on.

(3) References to, or to the release into the air of, a substance listed in this paragraph are to any of the following substances—

(a)oxides of sulphur and other sulphur compounds;

(b)oxides of nitrogen and other nitrogen compounds;

(c)oxides of carbon;

(d)organic compounds and partial oxidation products;

(e)metals, metalloids and their compounds;

(f)asbestos (suspended particulate matter and fibres), glass fibres and mineral fibres;

(g)halogens and their compounds;

(h)phosphorus and its compounds;

(i)particulate matter.

References to releases into water

7.  References in Part 2 to, or to the release into water of, a substance listed in this paragraph or to its release in a quantity which, in any period of 12 months, is greater than the background quantity by an amount specified in this paragraph are to the following substances and amounts—

Table
SubstanceAmount greater than the background quantity (in grammes) in any period of 12 months
*

Where both Altrazine and Simazine are released, the figure for both substances in aggregate is 350 grammes.

Mercury and its compounds200 (expressed as metal)
Cadmium and its compounds1,000 (expressed as metal)
All isomers of hexachlorocyclohexane20
All isomers of DDT5
Pentachlorophenol and its compounds350 (expressed as PCP)
Hexachlorobenzene5
Hexachlorobutadiene20
Aldrin2
Dieldrin2
Endrin1
Polychlorinated Biphenyls1
Dichlorvos0.2
1, 2—Dichloroethane2,000
All isomers of trichlorobenzene75
Atrazine350*
Simazine350*
Tributyltin compounds4 (expressed as TBT)
Triphenyltin compounds4 (expressed as TPT)
Trifluralin20
Fenitrothion2
Azinphos-methyl2
Malathion2
Endosulfan0.5

References to certain substances

8.—(1) References in Part 2 to a substance listed in this paragraph are to any of the following substances—

(a)alkali metals and their oxides and alkaline earth metals and their oxides;

(b)organic solvents;

(c)azides;

(d)halogens and their covalent compounds;

(e)metal carbonyls;

(f)organo-metallic compounds;

(g)oxidising agents;

(h)polychlorinated dibenzofuran and any congener thereof;

(i)polychlorinated dibenzo-p-dioxin and any congener thereof;

(j)polyhalogenated biphenyls, terphenyls and naphthalenes;

(k)phosphorus;

(l)pesticides.

(2) In this paragraph, “pesticide” means any chemical substance or preparation prepared or used for destroying any pest, including those used for—

(a)protecting plants or wood or other plant products from harmful organisms;

(b)regulating the growth of plants;

(c)giving protection against harmful creatures or rendering such creatures harmless;

(d)controlling organisms with harmful or unwanted effects on water systems, buildings or other structures, or on manufactured products; or

(e)protecting animals against ectoparasites.

(1)

1996 c. 56; section 4(1) was substituted by the Education Act 1997 (c. 44), section 51.

Back to top

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources