1. Where an application for registration is required under this section(1), that application must be made by the time provided under article 12.
2.—(1) Sub-paragraph (2) applies to a group (“A”) where the following change occurs in the post-qualification period—
(a)a significant group undertaking (“B”) leaves A; and
(b)B does not become a member of another group.
(2) In respect of the change—
(a)B must—
(i)apply to be registered as a participant in accordance with article 11; and
(ii)when doing so notify the administrator that it was a member of A and when it ceased to be so;
(b)A must—
(i)apply to be registered as a participant in accordance with article 11;
(ii)when doing so notify the administrator that B was a member of A and when it ceased to be so; and
(iii)in respect of the information required under paragraph 6 of Schedule 5, include the information which applied to B in the qualification year.
3.—(1) Sub-paragraph (2) applies to a group or undertaking (“C”) where the following change occurs in the post-qualification period—
(a)C becomes a significant group undertaking as a member of another group (“D”); and
(b)D is not required to register under article 24.
(2) In respect of the change—
(a)D must—
(i)apply for registration as a participant in accordance with article 11; and
(ii)when doing so notify the administrator that C is a member of D and when that occurred;
(b)C must not apply for registration as a participant;
(c)D is only a participant in respect of C; and
(d)D must with the application for registration provide in respect of the qualification year the information in sub-paragraph (3).
(3) The information referred to in sub-paragraph (2)—
(a)a list of the settled half hourly meters which measured the supply of electricity to D and the identification numbers of those meters; and
(b)in respect of the supply of electricity to D measured by settled half hourly meters and non-settled half hourly meters—
(i)whether or not the supply equalled or exceeded 3000 MWh and, if it did, the amount of the supply; and
(ii)if the supply equalled or exceeded 6000 MWh—
(aa)why D was not required to register as a participant; and
(bb)which deductions from a supply in section 4 and, if applicable, section 5 of Schedule 1 are applicable to the supply.
4.—(1) Sub-paragraphs (2) to (4) apply to a group or undertaking (“E”) where the following change occurs in the post-qualification period—
(a)E becomes a significant group undertaking as a member of another group (“F”); and
(b)F is required to register under article 24 but has not applied for registration.
(2) In respect of the change F must—
(a)apply for registration as a participant in accordance with article 11;
(b)when doing so notify the administrator that E is a member of F and when that occurred;
(c)in that notification F must inform the administrator whether or not F requests that E may apply for registration as a separate participant; and
(d)in respect of the information required under paragraph 6 of Schedule 5, include the information which applied to E in the qualification year.
(3) Where a request is made under sub-paragraph (2)(c), that must be treated as a request under article 25(2) and paragraphs (3) and (4) of that article apply.
(4) Except where sub-paragraph (3) applies, E must not apply for registration as a participant.
5.—(1) Sub-paragraphs (2) to (4) apply to a significant group undertaking (“G”) of a group (“H”) where—
(a)G becomes a significant group undertaking as a member of another group (“J”) in the post-qualification period; and
(b)H and J are groups to which article 27(2) applies.
(2) In respect of the change H and J must—
(a)apply for registration as participants in accordance with article 11;
(b)when doing so notify the administrator of the change and when it occurred; and
(c)in the notification by J, it must inform the administrator whether or not J requests that G may apply for registration as a separate participant.
(3) Where a request is made under sub-paragraph (2)(c), that must be treated as a request under article 25(2) and paragraphs (3) to (6) of that article apply.
(4) In respect of the information required under paragraph 6 of Schedule 5—
(a)H must include the information which applied to G in the qualification year;
(b)J must not include that information.
This section applies to an undertaking or a group of undertakings further to article 27(2).
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: