Search Legislation

The Electricity Capacity Regulations 2014

 Help about what version

What Version

 Help about advanced features

Advanced Features

Changes over time for: CHAPTER 2

 Help about opening options

Alternative versions:

Changes to legislation:

There are outstanding changes not yet made by the legislation.gov.uk editorial team to The Electricity Capacity Regulations 2014. Any changes that have already been made by the team appear in the content and are referenced with annotations. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.

View outstanding changes

Changes and effects yet to be applied to the whole Instrument associated Parts and Chapters:

Whole provisions yet to be inserted into this Instrument (including any effects on those provisions):

CHAPTER 2E+W+SSettlement Body decisions

DisputesE+W+S

74.—(1) Subject to paragraph (2), a disputing party may use the procedure in this Chapter to dispute any calculation or determination made by the Settlement Body under Part 6 or 7.

(2) The procedure in this Chapter may not be used to dispute the correctness of any data used in making a calculation or determination, which has been provided to the Settlement Body by another person under these Regulations or capacity market rules, except for non-BSC data provided by a capacity provider.

(3) In this Chapter, “disputing party” means, as appropriate, a supplier or a capacity provider.

(4) In paragraph (2), “non-BSC data” means data provided by or on behalf of a capacity provider which is not provided under the Balancing and Settlement Code, irrespective of whether the capacity provider is a party to the Balancing and Settlement Code.

Disputes noticeE+W+S

75.—(1) A disputing party may give a notice (“a disputes notice”) to the Settlement Body of a dispute.

(2) A disputes notice must—

(a)set out the matters giving rise to the dispute and the outcome sought by the disputing party; and

(b)be given not later than 28 days after the disputing party receives notice of the calculation or determination giving rise to the dispute.

Determination of disputesE+W+S

76.—(1) After receiving a disputes notice which complies with regulation 75(2), the Settlement Body must, subject to paragraph (2), review the disputed calculation or determination, and decide whether to uphold it or to substitute a different calculation or determination.

(2) The Settlement Body may, to assist in determining a dispute, appoint an independent person to consider the matter in dispute and provide a report on the matter, or an audit of any disputed calculation.

(3) The Settlement Body must, as soon as reasonably practicable after receiving a disputes notice, give notice to the disputing party whether it—

(a)is considering the disputed matter;

(b)has appointed an independent person to consider the disputed matter under paragraph (2); or

(c)has rejected the disputes notice on the ground that it does not comply with regulation 75(2).

(4) The Settlement Body must determine a dispute—

(a)where it commissions a report or audit under paragraph (2), not later than 28 days after receiving the report or audit; and

(b)in any other case, not later than 28 days after receiving the disputes notice.

(5) The Settlement Body must as soon as reasonably practicable after determining a dispute give a notice to the disputing party of its decision and the reason for that decision.

(6) The references in this regulation to “an independent person” include a panel of persons, either—

(a)established under an industry code; or

(b)appointed by the Settlement Body for the purpose of considering disputes under this Chapter,

provided that all the panel members who consider the dispute are independent from the Settlement Body and the disputing party.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Impact Assessments

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources