Article 35
Borough | Number of land shown on land plan | Purpose of which temporary possession may be taken | Relevant site or part of the authorised project |
---|---|---|---|
London Borough of Ealing | 1, 2, 3, 5, 8, 9, 10, 18, 19, 20, 22, 23, 24, 26, 28, 31, 31a, 32, 32a, 36 | Areas required for shaft construction; CSO interception works construction; ventilation equipment and structure construction; tunnel secondary lining; utility supplies, cranage, enclosures, concrete batching plant, workshops and stores, office, parking and welfare facilities, and vehicle and pedestrian circulation areas. Highway works to Canham Road, Stanley Gardens and Warple Way (part of Work No. 2b). Purposes ancillary or incidental to the above purposes. | Acton Storm Tanks |
London Borough of Hammersmith & Fulham | 101, 104, 105, 106, 107, 108, 109, 111, 112, 114, 115, 116, 117, 118 | Areas required for CSO drop shaft construction; Hammersmith connection tunnel construction; CSO interception works construction; utility supplies, cranage, enclosures, concrete batching plant, workshop and stores, office, parking and welfare facilities, and vehicle and pedestrian circulation areas. Highway works to Chancellor’s Road and Distillery Road. Utility works in Chancellor’s Road (part of Work No. 3c). Purposes ancillary or incidental to the above purposes. | Hammersmith Pumping Station |
London Borough of Richmond Upon Thames | 65, 65a, 65b, 66, 67, 68, 70, 72, 73, 76, 79, 85 | Areas required for CSO drop shaft construction; West Putney connection tunnel construction; CSO interception works construction; access road, utility supplies, cranage, enclosures, concrete batching plant, workshop and stores, office, parking and welfare facilities, and vehicle and pedestrian circulation areas. Highway works at junction of Queen Elizabeth Walk and private access road (part of Work No. 4c). Purposes ancillary or incidental to the above purposes. | Barn Elms |
London Borough of Wandsworth | 8, 9, 9a, 10, 11, 12, 12a, 12b, 12c, 13, 13a, 14, 14a, 15, 16, 20, 23, 25, 25a, 25b, 25c, 30, 32, 33, 34, 35, 36, 39, 40, 42, 44, 45, 46, 46a, 47, 47a, 48, 50 | Areas required for CSO drop shaft construction; Putney Bridge connection tunnel construction; CSO interception works construction; secondary lining; utility supplies, working area in the foreshore, temporary campshed, cranage, enclosures, concrete batching plant, workshop and stores, office, parking and welfare facilities, vehicle and pedestrian circulation areas, and relocation of houseboat. Separate area required for temporary slipway construction, use and removal, and works to existing river wall (part of Work No. 5d). Highway and utility works to Lower Richmond Road and the Embankment (part of Work No. 5c). Purposes ancillary or incidental to the above purposes. | Putney Embankment Foreshore |
London Borough of Hammersmith & Fulham | 124, 125, 127, 127a, 129, 130, 131, 132, 137, 138, 139, 140, 141, 141a, 142, 143, 144, 145, 146, 147, 147a, 147b, 148, 149, 150, 151, 152, 153, 154, 155, 156, 157, 158, 159, 160, 161, 162, 163, 173, 174, 176, 177 | Areas required for shaft construction; main tunnel construction; ventilation equipment and structure construction; tunnel secondary lining (part of Work No. 1b) and strengthening or replacing river walls including utility supplies, temporary jetty or campshed, cranage, enclosures, concrete batching plant, acoustic enclosure, other enclosures, workshop and stores, office, parking and welfare facilities, and vehicle and pedestrian circulation areas. Highway works to Carnwath Road and at the junction of Carnwath Road and Wandsworth Bridge Road. Utility works to Carnwath Road (part of Work No. 6b). Purposes ancillary or incidental to the above purposes. | Carnwath Road Riverside |
London Borough of Wandsworth | 75, 76, 77, 78, 79, 80, 81, 82, 84, 85, 86, 87, 88, 89, 91, 92, 95, 97, 99a, 100, 103, 104, 109, 110, 111, 117, 118, 119, 120, 121 | Areas required for CSO drop shaft construction; Frogmore connection tunnel construction; CSO interception works construction; strengthening and altering or replacing river walls, protection or relocation of sub-station including utility supplies, cranage, enclosures, concrete batching plant, temporary bridge, workshop and stores, office, parking and welfare facilities, utility supplies and vehicle and pedestrian circulation areas. Use of the Causeway (private road). Highway works to Dormay Street and at the junction of Dormay Street, the Causeway and Armoury Way. Utility works to the Causeway (part of Work No. 8c). Purposes ancillary or incidental to the above purposes. | Dormay Street |
London Borough of Wandsworth | 172, 173, 177, 179, 180 | Areas required for CSO drop shaft construction; CSO interception works construction; including utility supplies, cranage, enclosures, concrete batching plant, workshop and stores, office, parking and welfare facilities, and vehicle and pedestrian circulation areas. Highway and utility works to the junction of Buckhold Road and Neville Gill Close (part of Work No. 9b). Purposes ancillary or incidental to the above purposes. | King George’s Park |
London Borough of Wandsworth | 194, 196, 197, 198, 203, 204, 205, 206, 213, 214, 215, 216, 217, 218, 220, 222, 223 | Areas required for CSO drop shaft construction; Falconbrook connection tunnel construction; CSO interception works construction; including utility supplies, cranage, enclosures, concrete batching plant, workshop and stores, office, parking and welfare facilities, and vehicle and pedestrian circulation areas. Highway and utility works to York Road (part of Work No. 10c). Purposes ancillary or incidental to the above purposes. | Falconbrook Pumping Station |
Royal Borough of Kensington & Chelsea | 2, 3, 4, 9, 10, 11, 12, 13, 14, 15, 16, 18 | Areas required for CSO drop shaft construction; Lots Road connection tunnel construction; CSO interception works construction; including utility supplies, temporary campshed, cranage, enclosures, concrete batching plant, workshop and stores, office, parking and welfare facilities, and vehicle and pedestrian circulation areas. Highway works to Lots Road (part of Work No. 11c). Purposes ancillary or incidental to the above purposes. | Cremorne Wharf Depot |
Royal Borough of Kensington & Chelsea | 27, 28, 29, 31, 33, 40, 41, 45, 46, 47 | Areas required for CSO drop shaft construction; Ranelagh connection tunnel construction; CSO interception works construction; Low Level Sewer connection works construction; including temporary campshed, working area in the foreshore, cranage, enclosures, concrete batching plant, workshop and stores, office, parking and welfare facilities, and vehicle and pedestrian circulation areas. Highway and utility works to Chelsea Embankment (part of Work No. 12c). Purposes ancillary or incidental to the above purposes. | Chelsea Embankment Foreshore |
London Borough of Wandsworth | 234, 237a, 237b, 241, 242, 243, 244, 245, 246, 247, 248, 249, 252, 253, 254, 255, 256, 257, 258, 264, 265, 267, 268, 273, 274, 275, 276, 277, 278, 279, 280, 281, 282, 283, 284, 285, 286, 287, 288, 289, 290, 291, 292, 293, 294, 295, 296 | Areas required for shaft construction; main tunnel construction in two directions; ventilation equipment and structure construction, river wall works including utility supplies, temporary jetty, cranage, noise enclosures, other enclosures, concrete batching plant, workshop and stores, office, parking and welfare facilities, and vehicle and pedestrian circulation areas. Highway and utility works to Cringle Street and Kirtling Street (part of Work No. 13b). Purposes ancillary or incidental to the above purposes. | Kirtling Street |
London Borough of Wandsworth | 297, 299, 300, 301, 302, 308, 310a, 311a, 315, 316, 318, 319, 323, 324 | Areas required for CSO drop shaft construction; Heathwall/SWSR connection tunnel construction; two CSO interception works construction; working area in the foreshore; and river wall works including utility supplies, working area in the foreshore, provision of temporary campshed, cranage, enclosures, concrete batching plant, workshop and stores, office, parking and welfare facilities, and vehicle and pedestrian circulation areas. Areas for construction works associated with the temporary relocation of the Battersea Barge. Highway works to Nine Elms Lane (part of Work No. 14c). Purposes ancillary or incidental to the above purposes. | Heathwall Pumping Station |
London Borough of Lambeth | 5, 5a, 6, 7, 8, 9, 10, 10a, 11, 11a, 11b, 11c, 12, 13, 16, 18, 21, 24, 25, 26, 26a, 27, 31, 32, 34, 34a, 35, 40, 41, 42, 43, 44, 47, 49, 50, 51 | Areas required for CSO drop shaft construction; Clapham/Brixton connection tunnel construction; two CSO interception works construction; and protective works to slipway and walls including utility supplies, working areas in the foreshore, temporary campshed, cranage, enclosures, concrete batching plant, workshop and stores, office, parking and welfare facilities, accessways, and vehicle and pedestrian circulation areas. Highway works to Albert Embankment (part of Work No. 15c). Purposes ancillary or incidental to the above purposes. | Albert Embankment Foreshore |
City of Westminster | 13a, 14, 15, 16, 17, 17b, 19a, 21, 22, 23, 23a, 25, 26, 27, 28 | Areas required for CSO drop shaft construction; Regent Street connection tunnel construction; CSO interception works construction; Low Level Sewer connection works construction; working area in the foreshore, provision of temporary campshed, cranage, workshop and stores, office, parking and welfare facilities, and vehicle and pedestrian circulation areas. Areas for construction works associated with the relocation of Tattershall Castle. Highway and utility works to Victoria Embankment (part of Work No. 16c). | Victoria Embankment Foreshore |
City of London | 2, 3, 4, 5, 15a, 19, 19a, 23, 32, 34, 35, 39, 40, 45, 46 | Areas required for CSO drop shaft construction; CSO interception works construction; Low Level Sewer connection works construction; working area in the foreshore; provision of temporary campshed, cranage; workshop and stores, office, parking and welfare facilities, and vehicle and pedestrian circulation areas. Areas for construction works associated with the relocation of Blackfriars Millennium Pier. Areas for construction works associated with the relocation of the President. Highway and utility works to Victoria Embankment (part of Work No. 17b). | Blackfriars Bridge Foreshore |
London Borough of Southwark | 289, 290, 291, 292, 293, 297, 299, 300, 302 | Areas required for construction of drain down pumping station; connection chamber; flow measurement chamber; electrical switchgear and facilities building and associated pipework; including cranage, storage and welfare facilities. Highway and utility works in Maguire Street and Gainsford Street (part of Work No. 18). Purposes ancillary or incidental to the above purposes. | Shad Thames Pumping Station |
London Borough of Southwark | 15, 16, 17, 18, 21, 22, 24, 26, 27, 28, 31, 39, 40, 41, 42, 44, 45, 46, 47, 48, 49, 50, 51, 52, 61 | Areas required for shaft construction; main tunnel construction; and flood wall works including utility supplies, working area in the foreshore, cranage, acoustic and other enclosures, concrete batching plant, workshop and stores, office, parking and welfare facilities, and vehicle and pedestrian circulation areas. Highway works to Bevington Street. Utility works in Loftie Street, Chambers Street and East Lane (part of Work No. 19b). Purposes ancillary or incidental to the above purposes. | Chambers Wharf |
London Borough of Southwark | 286, 287, 288 | Areas required for CSO drop shaft construction; CSO interception works construction; including utility supplies, cranage, enclosures, concrete batching plant, workshop and stores, office, parking and welfare facilities, and vehicle and pedestrian circulation areas. Highway and utility works to Chilton Grove, Yeoman Street and Croft Street (part of Work No. 21b). Purposes ancillary or incidental to the above purposes. | Earl Pumping Station |
London Borough of Lewisham | 2, 4, 5, 7, 8, 9, 10, 15, 16, 20, 21, 22, 23, 24 | Areas required for CSO drop shaft construction; CSO interception works construction; including utility supplies, cranage, enclosures, concrete batching plant, workshop and stores, office, parking and welfare facilities, and vehicle and pedestrian circulation areas. Highway and utility works to Chilton Grove, Yeoman Street and Croft Street (part of Work No. 21b). Purposes ancillary or incidental to the above purposes. | Earl Pumping Station |
London Borough of Lewisham | 150, 151, 152, 153, 154, 158, 164, 165, 166, 167, 168, 169, 170, 172, 174, 175, 177, 180, 181, 182 | Areas required for CSO drop shaft construction; CSO interception works construction including cranage, enclosure, concrete batching plant, workshop and stores, office, parking and welfare facilities, vehicle and pedestrian circulation areas and fire assembly points. Areas for two fire assembly points for school. Highway works to Crossfield Street and Coffey Street. Highway and utility works to Deptford Church Street (part of Work No. 22b). Purposes ancillary or incidental to the above purposes. | Deptford Church Street |
Royal Borough of Greenwich | 1, 2, 3, 4 | Areas required for CSO drop shaft construction; CSO interception works construction; construction including cranage, enclosure, concrete batching plant, workshop and stores, office, parking and welfare facilities, vehicle and pedestrian circulation areas and fire assembly points. Areas for two fire assembly points for school. Highway works to Crossfield Street and Coffey Street. Highway and utility works in Deptford Church Street (part of Work No. 22b). Purposes ancillary or incidental to the above purposes. | Deptford Church Street |
Royal Borough of Greenwich | 11, 12, 15, 16, 18, 18a, 19, 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 31, 32, 33, 34, 46, 47, 48, 49 | Areas required for CSO drop shaft construction; Greenwich connection tunnel construction; CSO interception works construction; tunnel secondary lining; and river wall works including utility supplies, cranage, acoustic and other enclosures, concrete batching plant, workshop and stores, office, parking and welfare facilities, and vehicle and pedestrian circulation areas. Highway works to Norman Road (part of Work No. 23b). Purposes ancillary or incidental to the above purposes. | Greenwich Pumping Station |
London Borough of Tower Hamlets | 21, 21a, 22, 22a, 23, 23a, 24, 25, 32, 33, 34, 35, 36, 36a, 37 | Areas required for CSO drop shaft construction; CSO interception works construction; river wall works and replacement or refurbishment of park facilities including utility supplies, working area in the foreshore, campshed, cranage, enclosures, concrete batching plant, workshop and stores, office, parking and welfare facilities, vehicle and pedestrian circulation areas. Highway works to Glamis Road. Utility works in Glamis Road and The Highway (part of Work No. 24b). Purposes ancillary or incidental to the above purposes. | King Edward Memorial Park Foreshore |
London Borough of Tower Hamlets | 210, 212, 213, 218, 219, 220, 221, 222, 224, 225 | Areas required for construction of chamber, kiosk, ventilation column and associated pipework; cranage; storage and welfare facilities. Highway and utility works in Ratcliffe Lane (part of Work No. 25). Purposes ancillary or incidental to the above purposes. | Bekesbourne Street |
London Borough of Newham | 21, 22, 23, 24, 25, 26, 28, 33 | Areas required for shaft construction; ventilation equipment and structure construction; tunnel secondary lining; including utility supplies, cross-river footbridge, cranage, enclosures, concrete batching plant, workshop and stores, office, parking and welfare facilities, and vehicle and pedestrian circulation areas. Purposes ancillary or incidental to the above purposes. | Abbey Mills Pumping Station |
London Borough of Newham | 34, 35, 36, 37, 38, 39, 48, 52, 53, 58, 59, 60, 61, 62, 63, 64, 65, 66, 66a, 67, 68, 69, 70, 71, 72, 78, 79, 82 | Areas required for siphon tunnel construction; shafts construction; other permanent works construction; including utility supplies, cranage, enclosures, concrete batching plant, workshop and stores, office, parking and welfare facilities, and vehicle and pedestrian circulation areas. Purposes ancillary or incidental to the above purposes. | Beckton Sewage Treatment Works |
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: