25.—(1) The authorised development must not be commissioned until a written scheme for the management and mitigation of odour emissions has been submitted to and, after consultation with Selby District Council, approved by the planning authority.
(2) The scheme submitted and approved must be in accordance with the principles set out in the odour management plan contained in Appendix 8B to the environmental statement.
(3) The authorised development must not be brought into commercial use until the approved scheme has been implemented.
(4) The approved scheme must be maintained throughout the operation of the authorised development.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: