29.—(1) The authorised development must not be commissioned until—
(a)a written scheme to prevent the infestation or emanation of insects or vermin from the authorised development has been submitted to and approved by the planning authority; and
(b)the approved scheme has been implemented.
(2) The approved scheme must be maintained throughout the operation of the authorised development.
(3) In subparagraph (1), “insects and vermin” excludes insects and vermin that are wild animals included in Schedule 5 to the Wildlife and Countryside Act 1981(1) (animals which are protected), unless they are included in respect of section 9(5) of that Act only.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: