Articles 2 and 6

SCHEDULE 1SCHEDULED WORKS

In the City of London -

Work No.1 - A railway 662 metres in length in tunnel, being a realignment of part of the southbound railway of the Company’s Northern Line, commencing by a junction with the southbound railway beneath a point 16 metres north of the junction of Gresham Street with Lothbury, passing in a southerly direction and terminating by a junction with the southbound railway beneath a point 39 metres south of the bridge carrying King William Street over Lower Thames Street.

Work No.1A - A passenger subway linking the proposed passenger platform forming part of Work No.1 to the Company’s existing Northern Line southbound passenger platform at Bank station, commencing by a junction with Work No.1 beneath a point 37 metres south-west of the junction of Sherborne Lane with King William Street and terminating beneath a point 7 metres south-east of that road junction.

Work No.1B - A passenger subway linking the proposed passenger platform forming part of Work No.1 to the Company’s existing Northern Line southbound platform at Bank station, commencing by a junction with Work No.1 beneath a point 40 metres south-west of the junction of Sherborne Lane with King William Street and terminating beneath a point 17 metres south-east of that road junction.

Work No. 1C - A passenger subway linking the proposed passenger platform forming part of Work No.1 to the Company’s existing Northern Line southbound platform at Bank station, commencing beneath a point 8 metres north-west of the junction of Abchurch Lane with King William Street and terminating at a junction with Work No. 1 beneath a point 38 metres west of that road junction.

Work No. 1D - A passenger subway linking the proposed passenger platform forming part of Work No.1 to the Company’s existing Northern Line southbound platform at Bank station, commencing beneath a point 28 metres south-east of the junction of Abchurch Lane with King William Street and terminating at a junction with Work No. 1 beneath a point 47 metres south-west of that road junction.

Work No. 2 – A passenger subway incorporating two banks of triple escalators between a proposed station entrance hall on the north side of Cannon Street to a passenger subway (Work No.1C) commencing at a point 19 metres north of the junction of Nicholas Lane with Cannon Street and terminating by a junction with Work No.1C beneath a point 15 metres west of the junction of Abchurch Lane with King William Street.

Work No. 3 – A passenger subway incorporating a bank of triple escalators between the existing Docklands Light Railway passenger subway at Bank station to the Company’s Northern Line passenger concourse commencing by a junction with Work No.1B beneath a point 22 metres south-west of the junction of Sherborne Lane with King William Street and terminating at the Docklands Light Railway passenger concourse beneath a point 12 metres south-west of the junction of Abchurch Lane with King William Street.

Work No. 4 - A passenger subway incorporating a moving passenger walkway between the passenger subway forming Work No.1A and the proposed passenger subway to the Company’s Central Line forming Work No. 5, commencing beneath a point 27 metres west of the junction of Prince’s Street with Threadneedle Street and terminating by a junction with Work No.1A at a point 22 metres south-west beneath the junction of Sherborne Lane with King William Street.

Work No. 5 – A passenger subway incorporating a bank of triple escalators between the passenger subway forming Work No.4 and the Company’s Central Line, commencing beneath a point 7 metres east of the junction of Prince’s Street with Threadneedle Street and terminating beneath a point 34 metres west of that road junction.

Work No. 6 - A passenger subway forming a reconstruction and enlargement of the existing passenger subway connecting the passenger subway forming Work No.5 to the Company’s Central Line passenger platforms at Bank station, commencing beneath a point 11 metres south-east of the junction of Prince’s Street with Threadneedle Street and terminating beneath a point 8 metres north of that road junction.

Work No. 7 - A tunnel for construction purposes commencing beneath a point 20 metres south of the junction of Sherborne Lane with King William Street and terminating beneath a point 11 metres south-east of that road junction.

Work No. 8 - A tunnel for construction purposes commencing beneath a point 14 metres west of the junction of Abchurch Lane with King William Street and terminating beneath a point 7 metres north of that road junction.

Work No. 9 – A tunnel for construction purposes commencing beneath a point 29 metres south of the junction of Abchurch Lane with King William Street and terminating beneath a point 22 metres south-east of that road junction.

Work No. 10 - A tunnel for construction and maintenance purposes, commencing by a junction with Work No.1 at a point 34 metres east of the junction of Abchurch Lane with Cannon Street and terminating at a point 10 metres north of the junction of Nicholas Lane with King William Street. Work No. 10 includes alterations to the headwalls of the Company’s existing Northern Line southbound and northbound platforms and to the Company’s existing escalator tunnel to Monument Station to enlarge the existing passenger subway.

Work No. 11 - A tunnel for construction and maintenance purposes linking Work No.1 to the Company’s existing Northern Line southbound tunnel, commencing by a junction with Work No.1 beneath a point 28 metres south of the junction of Prince’s Street with Moorgate and terminating beneath a point 28 metres south of that road junction.

Work No. 12 - A tunnel for construction and maintenance purposes linking Work No.1 to the Company’s existing Northern Line southbound tunnel, commencing by a junction with Work No.1 beneath a point 24 metres north-west of the junction of King William Street with Arthur Street and terminating beneath a point 20 metres north-east of that road junction.

Work No. 13A - A passenger subway linking the Docklands Light Railway arrival platform to the concourse of that railway at Bank station, commencing beneath a point 36 metres north-west of the junction of Abchurch Lane with King William Street and terminating beneath a point 32 metres north-west of that road junction.

Work No. 13B - A passenger subway linking the Docklands Light Railway departure platform to the concourse of that railway at Bank station, commencing beneath a point 32 metres north-west of the junction of Abchurch Lane with King William Street and terminating beneath a point 30 metres north-west of that road junction.

Work No. 14 - A passenger subway linking the Docklands Light Railway arrival and departure platforms to the concourse of that railway at Bank station, commencing beneath a point 20 metres south-west of the junction of Abchurch Lane with King William Street and terminating beneath a point 7 metres south-east of that junction.

Work No. 15 - A passenger subway linking the Docklands Light Railway arrival platform to the concourse of that railway at Bank station, commencing beneath a point 30 metres south of the junction of Abchurch Lane with King William Street and terminating beneath a point 26 metres south of that road junction.

Work No. 16 - A passenger subway connecting the Company’s Central Line eastbound and westbound passenger platforms at Bank station, commencing beneath a point 21 metres north-east of junction of Walbrook with Queen Victoria Street and terminating beneath a point 15 metres north-east of that road junction.

Work No. 17 - A tunnel for services between Work No.4 and the Company’s existing Central Line ticket hall, commencing beneath a point 29 metres south-west of junction of Prince’s Street with Threadneedle Street and terminating beneath a point 6 metres south of that road junction.

Work No.18 – A passenger subway connecting Work No.1A to the Company’s existing passenger lift (No. D6) commencing beneath a point 20 metres south of the junction of St Swithin’s Lane and King William Street and terminating beneath a point 10 metres south of the junction of Sherborne Lane with King William Street.

Work No. 19 - A tunnel for construction and maintenance purposes linking Work No.1 to Work Nos. 4 and 5, commencing by a junction with Work No.1 beneath a point 65 metres north-west of the junction of Poultry with King William Street and terminating beneath a point 27 metres west of that road junction.

Work No. 20 - A tunnel for construction and maintenance purposes, commencing by a junction with Work No. 3 beneath a point 33 metres south of the junction of Sherborne Lane with King William Street and terminating at point 26 metres south of that road junction.

Work No. 21 - A passenger subway between the proposed lift shaft and Work No.1D, commencing beneath a point 31 metres south of the junction of Abchurch Lane with King William Street and terminating at point 36 metres south of that junction.

Work No. 22 - A tunnel for operational services between the proposed shaft to incorporate a proposed lift and Work No.1D, commencing beneath a point 34 metres south of the junction of Abchurch Lane with King William Street and terminating at point 38 metres south of that road junction.

Work No. 23 - A tunnel for construction purposes, linking Work No.1C with Work No. 3, commencing by a junction with Work No.3 beneath a point 27 metres south of the junction of Sherborne Lane with King William Street and terminating at point 24 metres west of the junction of Abchurch Lane with King William Street.

Work No. 24 - A tunnel for operational services linking Work No 10 to the proposed lift shaft, commencing by a junction with Work No. 1 at a point 16 metres west of the junction of Nicholas Lane with King William Street and terminating at a point 14 metres west of that road junction.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources