Search Legislation

The Town and Country Planning (General Permitted Development) (England) Order 2015

 Help about what version

What Version

  • Latest available (Revised)
  • Original (As made)
 Help about advanced features

Advanced Features

Changes over time for: Cross Heading: Class BB – moveable structures for historic visitor attractions and listed pubs, restaurants etc

 Help about opening options

Changes to legislation:

There are currently no known outstanding effects for the The Town and Country Planning (General Permitted Development) (England) Order 2015, Cross Heading: Class BB – moveable structures for historic visitor attractions and listed pubs, restaurants etc. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

[F1Class BB – moveable structures for historic visitor attractions and listed pubs, restaurants etcE+W

Permitted developmentE+W

BB.  The provision of one moveable structure within the curtilage, and for the purposes, of—

(a)a listed building used for a purpose within—

(i)article 3(6)(p) or (q) (drinking establishments etc.) of the Use Classes Order; or

(ii)Class E(b) (sale of food and drink etc.) of Schedule 2 to that Order; or

(b)a historic visitor attraction.

Development not permittedE+W

BB.1.   Development is not permitted by Class BB—

(a)on land which is or forms part of a scheduled monument or land within its curtilage;

(b)if any part of the moveable structure would be within 2 metres of the curtilage of any adjacent land that is used for a purpose within Part C (residential uses) of Schedule 1 to the Use Classes Order;

(c)if it would result in provision of a moveable structure being made within the curtilage of a building under Class BB on a total of more than 120 days in the relevant period;

(d)if the height of the moveable structure would exceed 3 metres;

(e)if the footprint of the moveable structure would exceed the lesser of—

(i)50% of the footprint of the building, or

(ii)50 square metres;

(f)if the moveable structure is used for the display of an advertisement.

ConditionsE+W

BB.2.  Development is permitted by Class BB subject to the following conditions—

(a)where the moveable structure provided under Class BB is removed, the land must, as soon as reasonably practicable and so far as reasonably practicable, be reinstated to its original condition;

(b)before a moveable structure is provided under Class BB (whether for the first time, or following the expiry of the relevant period), the developer must apply to the local planning authority for a determination as to whether the prior approval of the authority will be required as to—

(i)the siting of the moveable structure, and

(ii)the method by which it is to be installed,

and paragraph BB.3 applies in relation to that application.

Procedure for applications for prior approval under Class BBE+W

BB.3.(1) This paragraph applies where under Class BB a developer is required to make an application to the local planning authority for a determination as to whether the prior approval of the authority will be required.

(2) The application must be accompanied by—

(a)a written description of the proposed development;

(b)a plan indicating the site and showing the proposed development;

(c)a statement setting out the proposed methods of—

(i)installing the moveable structure; and

(ii)reinstating the land to its original condition once the moveable structure is removed;

(d)the developer’s contact address; and

(e)the developer’s email address if the developer is content to receive communications electronically,

together with any fee required to be paid.

(3) The local planning authority may refuse an application where, in the opinion of the authority—

(a)the proposed development does not comply with, or

(b)the developer has provided insufficient information to enable the authority to establish whether the proposed development complies with,

any conditions and limitations specified in Class BB as being applicable to the development in question.

(4) Sub-paragraphs (5) to (7) and (9) do not apply where a local planning authority refuses an application under sub-paragraph (3) and for the purposes of section 78 (appeals) of the Act such a refusal is to be treated as a refusal of an application for approval.

(5) On receipt of the application, the local planning authority must consult Historic England.

(6) The local planning authority must notify Historic England specifying the date by which they must respond (being not less than 21 days from the date the notice is given).

(7) The local planning authority must give notice of the proposed development—

(a)by site display in at least one place on or near the land to which the application relates for not less than 21 days of a notice which—

(i)describes the proposed development;

(ii)provides the address of the proposed development;

(iii)specifies the date by which representations are to be received by the local planning authority; or

(b)by serving a notice in that form on any adjoining owner or occupier.

(8) The local planning authority may require the developer to submit such information as the authority may reasonably require in order to determine the application.

(9) The local planning authority must, when determining an application—

(a)take into account any representations made to them as a result of consultation under sub-paragraph (5) and any notice given under sub-paragraph (7); and

(b)have regard to the National Planning Policy Framework issued by the Ministry of Housing, Communities and Local Government in July 2021, so far as relevant to the subject matter of the prior approval, as if the application were a planning application.

(10) The development must not begin before the occurrence of one of the following—

(a)the receipt by the applicant from the local planning authority of a written notice of their determination that such prior approval is not required;

(b)the receipt by the applicant from the local planning authority of a written notice giving their prior approval; or

(c)the expiry of 56 days following the date on which the application referred to in sub-paragraph (2) was received by the local planning authority without the authority notifying the applicant as to whether prior approval is given or refused.

(11) The development must be carried out—

(a)where prior approval is required, in accordance with the details approved by the local planning authority;

(b)where prior approval is not required, or where sub-paragraph (10)(c) applies, in accordance with the details provided in the application referred to in sub-paragraph (2), unless the local planning authority and the developer agree otherwise in writing.

(12) The local planning authority may grant prior approval unconditionally or subject to conditions reasonably related to the subject matter of the prior approval.

(13) When computing the number of days in sub-paragraph (7)(a), any day which is a public holiday must be disregarded.

Interpretation of Class BBE+W

BB.4.  For the purposes of Class BB—

footprint”, in relation to a building or a moveable structure, means the total area of ground covered by the building or moveable structure;

historic visitor attraction” means a listed building accessible by members of the public (whether or not for an entry fee) for the purposes of promoting their enjoyment, and advancing their knowledge, of the building;

original condition”, in relation to land on which a moveable structure is provided, means the condition of the land before the moveable structure was provided;

relevant period” means the period of 12 months beginning with the day on which one of the events described in paragraph BB.3(10) occurs.]

Back to top

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open The Whole Schedule

The Whole Schedule you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Schedule as a PDF

The Whole Schedule you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Impact Assessments

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources