- Latest available (Revised)
- Original (As made)
This is the original version (as it was originally made).
Regulation 35(1)
1. This Schedule applies in relation to every large combustion plant.
2.—(1) In this Schedule—
“combustion plant” has the meaning given in Article 3(25) of the Industrial Emissions Directive;
“large combustion plant” means a combustion plant with a total rated thermal input of 50 or more megawatts to which Chapter III of the Industrial Emissions Directive applies.
(2) When interpreting the Industrial Emissions Directive for the purposes of this Schedule—
(a)except where defined in this paragraph, an expression that is defined in Part 1 of these Regulations has the meaning given in that Part;
(b)the competent authority is—
(i)for the purposes of exercising a judgement as to whether there is an overriding need to maintain energy supplies under Articles 30(6) and 37 of the Industrial Emissions Directive, the appropriate authority;
(ii)otherwise, the regulator;
(c)“permit” means environmental permit.
3. The regulator must exercise its relevant functions so as to ensure compliance with the following provisions of the Industrial Emissions Directive—
(a)Article 29;
(b)Article 30(1) to (8), except the second sub-paragraph of Article 30(5) and the last sub-paragraph of Article 30(6);
(c)Article 31(1) and (2);
(d)Article 32(2) and (3);
(e)Article 33 except 33(2);
(f)Article 34(1) and (2);
(g)Article 35(1);
(h)Article 37;
(i)Article 38;
(j)Article 39;
(k)Article 40.
4. The regulator must—
(a)immediately inform the appropriate authority of any derogation under Article 30(5) of the Industrial Emissions Directive;
(b)immediately inform the appropriate authority if it considers that a derogation in accordance with Articles 30(6) or 37(2) of the Industrial Emissions Directive is or might be appropriate.
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: