Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Regulations 14, 16 and 18

SCHEDULE 3E+W+SAccess charging

This schedule has no associated Explanatory Memorandum

Principles of access chargingE+W+S

1.—(1) The infrastructure manager must ensure that the application of the charging scheme—

(a)complies with the rules set out in the network statement produced in accordance with regulation 13; and

(b)results in equivalent and non-discriminatory charges for different railway undertakings that perform services of an equivalent nature in a similar part of the market.

(2) The calculation of the charge may in particular take into account the mileage, composition of the train and any specific requirements in terms of such factors as speed, axle load and the degree or period of utilisation of the railway infrastructure.

(3) Except where specific arrangements are made in accordance with paragraph 3, the infrastructure manager must ensure that the charging system in use is based on the same principles over the whole of the network.

(4) Without prejudice to sub-paragraph (8) the charges for the minimum access package and track access to service facilities referred to in paragraphs 1 and 2 of Schedule 2 must be set at the cost that is directly incurred as a result of operating the train service.

(5) From 2nd August 2019 or earlier, the infrastructure manager must [F1, subject to sub-paragraphs (5A) and 5(B),] calculate the cost under sub-paragraph (4) or, as the case may be, under the first paragraph of Article 4 of the Channel Tunnel charging framework, in accordance with Commission Implementing Regulation (EU) 2015/909 of 12th June 2015 on the modalities for the calculation of the cost that is directly incurred as a result of operating the train service M1.

[F2(5A) For the purposes of the calculation of direct costs on a network-wide basis, referred to in paragraph 1 of Article 3 of the Commission Implementing Regulation referred to in sub-paragraph (5), the infrastructure manager may apply the costs of efficient service provision.

(5B) For the purposes of calculating the direct unit costs referred to in paragraph 1 of Article 5 of the Commission Implementing Regulation referred to in sub-paragraph (5), the infrastructure manager may modulate the average direct unit costs to take into account the different levels of wear and tear caused to the infrastructure according to one or more of the parameters listed in paragraph 2 of Article 5 of that Commission Implementing Regulation.]

(6) The charge imposed for track access within service facilities referred to in paragraph 2 of Schedule 2 and the supply of services in such service facilities must not exceed the cost of providing it, plus a reasonable profit.

(7) If the additional or ancillary services referred to in paragraphs 3 and 4 of Schedule 2 are offered by only one supplier the charge imposed for the supply of those services must not exceed the cost of providing the service, plus a reasonable profit.

(8) The infrastructure charge may include a charge to reflect the scarcity of capacity of the identifiable segment of the infrastructure during periods of congestion.

(9) The charges referred to in sub-paragraphs (4) and (8) may be averaged over a reasonable spread of train services and times, but the relative magnitudes of the railway infrastructure charges must be related to the costs attributable to the services.

Exceptions to the charging principlesE+W+S

2.—(1) In order to obtain full recovery of the costs incurred the infrastructure manager, with the approval of the Office of Rail and Road or, in relation to a rail link facility, the Secretary of State, may levy mark-ups on the basis of efficient, transparent and non-discriminatory principles, whilst guaranteeing optimum competitiveness, in particular in respect of rail market segments.

(2) For the purposes of this paragraph—

(a)approval given by the Secretary of State in relation to a rail link facility must be given through the development agreement; and

(b)approval given by the Office of Rail and Road must—

(i)in relation to railway infrastructure subject to the access charges review, be given as part of that review; and

(ii)in relation to any other railway infrastructure, be given in such form or manner as the Office may require.

(3) The effect of sub-paragraphs (1) and (2) must not be to exclude the use of infrastructure by market segments which can pay at least the cost that is directly incurred as a result of operating the railway service, plus a rate of return which the market can bear.

(4) The charging system must respect the productivity increases achieved by applicants.

(5) Before approving the levy of a mark-up under sub-paragraph (1) the Office of Rail and Road or, as the case may be, the Secretary of State, must ensure that the infrastructure manager evaluates the relevance of a mark-up for the specific market segments, considering at least the pairs listed in sub-paragraph (10) and retaining the relevant ones.

(6) The list of market segments to be considered by the infrastructure manager under sub-paragraph (5) must contain at least the three following segments: freight services, passenger services within the framework of a public service contract and other passenger services.

(7) In addition to the market segments considered under sub-paragraph (5), the infrastructure manager may consider further market segments according to commodity or passengers transported.

(8) Market segments in which railway undertakings are not currently operating but in which they may provide services during the period of validity of the charging system must also be defined; the infrastructure manager must not include a mark-up in the charging system for those market segments.

(9) The list of market segments must be published in the network statement and reviewed at least every five years; the Office of Rail and Road must control that list in accordance with paragraph (2) of regulation 31.

(10) The pairs referred to in sub-paragraph (5) are—

(a)passenger versus freight services;

(b)trains carrying dangerous goods versus other freight trains;

(c)domestic versus international services;

(d)combined transport versus direct trains;

(e)urban or regional versus interurban passenger services;

(f)block trains versus single wagon load trains; and

(g)regular versus occasional train services.

3.—(1) Subject to sub-paragraph (2), for specific investment projects completed—E+W+S

(a)since 1988; or

(b)following the coming into force of these Regulations,

the infrastructure manager may set or continue to set higher charges on the basis of the long-term costs of the project.

(2) For sub-paragraph (1) to apply—

(a)the project must increase efficiency or cost-effectiveness; and

(b)the project must be one that could not otherwise have been undertaken without the prospect of such higher charges.

(3) A charging arrangement to which sub-paragraph (1) applies may incorporate agreements on the sharing of the risk associated with new investments.

4.—(1) An infrastructure manager's average and marginal charges for equivalent uses of the railway infrastructure must be comparable, and comparable services in the same market segment must be subject to the same charges.E+W+S

(2) The network statement produced by the infrastructure manager in accordance with regulation 13 must demonstrate that the charging system meets the requirements in sub-paragraph (1) in so far as this can be done without the disclosure of commercially confidential information.

5.  If an infrastructure manager intends to modify the essential elements of the charging system referred to in paragraph 2 that infrastructure manager must make such modifications public at least three months in advance of the deadline for the publication of the network statement in accordance with regulation 13(9).E+W+S

DiscountsE+W+S

6.—(1) F3... Notwithstanding paragraph 1(4) and (5) of this Schedule, any discount on the charges levied on a user of railway infrastructure by the infrastructure manager, for any service, must comply with the principles set out in this paragraph.

(2) Except where sub-paragraph (3) applies, discounts must be limited to the actual saving of the administrative cost to the infrastructure manager and, in determining the level of discount to be applied, no account may be taken of cost savings already incorporated in the charge levied.

(3) The infrastructure manager may introduce schemes available to all users of the railway infrastructure, with reference to specified traffic flows, granting time limited discounts to encourage the development of new rail services, or discounts encouraging the use of considerably under-utilised lines.

(4) The discounts available must be in accordance with the access charges review, where it applies, or, in the case of a rail link facility, the development agreement.

(5) Discounts may relate only to charges levied for a specified railway infrastructure section.

(6) Similar discount schemes must be applied to similar services.

(7) Discount schemes must be applied in a non-discriminatory manner to any railway undertaking.

Performance SchemesE+W+S

7.—(1) The basic principles referred to in regulation 16(3) are as follows.

(2) In order to achieve an agreed level of performance and not to endanger the economic viability of a service, the infrastructure manager must agree with applicants the main parameters of the performance scheme, in particular the value of delays, the thresholds for payments due under the performance scheme relative both to individual train runs and to all train runs of a railway undertaking in a given period of time.

(3) The infrastructure manager must communicate to the railway undertakings the working timetable, on the basis of which delays will be calculated, at least five days before the train run, except that the infrastructure manager may apply a shorter notice period in case of force majeure or late alterations of the working timetable.

(4) All delays must be attributable to one of the following delay classes and sub-classes—

(a)operation/planning management attributable to the infrastructure manager—

(i)timetable compilation;

(ii)formation of train;

(iii)mistakes in operations procedure;

(iv)wrong application of priority rules;

(v)staff; or

(vi)other causes;

(b)railway infrastructure installations attributable to the infrastructure manager—

(i)signalling installations;

(ii)signalling installations at level crossings;

(iii)telecommunications installations;

(iv)power supply equipment;

(v)track;

(vi)structures;

(vii)staff; or

(viii)other causes;

(c)civil engineering causes attributable to the infrastructure manager—

(i)planned construction work;

(ii)irregularities in execution of construction work;

(iii)speed restriction due to defective track; or

(iv)other causes;

(d)causes attributable to other infrastructure managers—

(i)caused by previous infrastructure manager; or

(ii)caused by next infrastructure manager;

(e)commercial causes attributable to the railway undertaking—

(i)exceeding the stop time;

(ii)request of the railway undertaking;

(iii)loading operations;

(iv)loading irregularities;

(v)commercial preparation of train;

(vi)staff; or

(vii)other causes;

(f)rolling stock attributable to the railway undertaking—

(i)roster planning/re-rostering;

(ii)formation of train by railway undertaking;

(iii)problems affecting coaches (passenger transport);

(iv)problems affecting wagons (freight transport);

(v)problems affecting cars, locomotives and rail cars;

(vi)staff; or

(vii)other causes;

(g)causes attributable to other railway undertakings—

(i)caused by next railway undertaking; or

(ii)caused by previous railway undertaking;

(h)external causes attributable to neither infrastructure manager nor railway undertaking—

(i)strike;

(ii)administrative formalities;

(iii)outside influence;

(iv)effects of weather and natural causes;

(v)delay due to external reasons on the next network; or

(vi)other causes; or

(i)secondary causes attributable to neither infrastructure manager nor railway undertaking—

(i)dangerous incidents, accidents and hazards;

(ii)track occupation caused by the lateness of the same train;

(iii)track occupation caused by the lateness of another train;

(iv)turn-around;

(v)connection; or

(vi)further investigation needed.

(5) Wherever possible, delays must be attributed to a single organisation, considering both the responsibility for causing the disruption and the ability to re-establish normal traffic conditions.

(6) The calculation of payments must take into account the average delay of train services of similar punctuality requirements.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Impact Assessments

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources