12.—(1) The requirements referred to in article 11(2)(a) in relation to Condition A are that the measure—

(a)is installed at domestic premises;

(b)results in the reduction in the cost of heating those premises to 21 degrees Celsius in the main living areas and 18 degrees Celsius in all other areas, or in the case of a data light measure, is reasonably expected to result in such a reduction;

(c)is completed on or after 1st April 2022 and before 1st April 2026;

(d)except in the case of a repair, is installed at—

(i)premises erected before 1st April 2022; or

(ii)premises which were first occupied as domestic premises before the day on which the installation is completed;

(e)is not funded by any grant from public funds; and

(f)either—

(i)forms part of an ECO4 project which—

(aa)meets the requirement concerning the assessment of energy efficiency in paragraph (2); and

(bb)does not include an in-fill measure, ECO3 interim delivery action or surplus action; or

(ii)is an in-fill measure which meets the requirement concerning the assessment of energy efficiency in paragraph (3).

(2) An ECO4 project meets the requirement concerning the assessment of energy efficiency if—

(a)where the project is an ECO4 project which consists of a district heating connection only or a district heating connection and one or more novel data light measures only—

(i)a SAP assessment is performed before the day on which the first measure in the project is completed for the purpose of calculating the SAP rating of the premises; and

(ii)a pre-installation EPC is issued for the premises;

(b)where the project is an ECO4 project which consists of one or more novel data light measures only—

(i)an RdSAP assessment is performed before the day on which the first measure in the project is completed for the purpose of calculating the SAP rating of the premises; and

(ii)a pre-installation EPC is issued for the premises;

(c)where the project is an ECO4 project which does not fall within sub-paragraph (a) or (b), an RdSAP assessment is performed before the day on which the first measure in the project is completed for the purpose of calculating the SAP rating of the premises.

(3) An in-fill measure meets the requirement concerning the assessment of energy efficiency if—

(a)where the in-fill measure is a district heating connection—

(i)a SAP assessment is performed before the day on which the in-fill measure is completed for the purpose of calculating the SAP rating of the premises; and

(ii)a pre-installation EPC is issued for the premises;

(b)where the in-fill measure does not fall within sub-paragraph (a), an RdSAP assessment is performed before the day on which the in-fill measure is completed for the purpose of calculating the SAP rating of the premises.

(4) In paragraphs (2) and (3), references to a “district heating connection” do not include a connection to a district heating system that uses a shared ground loop.

(5) In this article, “grant from public funds” means a grant made by a public authority or by any person distributing funds on behalf of a public authority.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Impact Assessments

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources