46.  In this Part—

adjusted cost savings” means, in relation to a data light measure or a standard alternative methodology measure, the adjusted cost savings calculated in accordance with article 75(2)(b);

basic heating repair or replacement measure” means a qualifying action that is—

(a)

the repair of—

(i)

an efficient boiler;

(ii)

an efficient heating system;

(iii)

a renewable heating system; or

(iv)

equipment for the generation of heat wholly or partly from biofuel, oil or liquefied petroleum gas,

but is not the repair of an electric storage heater or heating controls;

(b)

the replacement of an efficient boiler with another efficient boiler; or

(c)

the replacement of an efficient heating system, other than an electric storage heater, with another efficient heating system of the same kind;

building fabric repair allowance” means, in relation to a participant, the amount equal to 0.5% of the participant’s total home-heating cost reduction obligation;

“building fabric repair expenditure”—

(a)

in connection with an ECO4 project has the meaning given in article 62;

(b)

in connection with a qualifying action has the meaning given in article 74(3) and (4);

“building fabric repair increase”—

(a)

in relation to an ECO4 project has the meaning given in article 55(3);

(b)

in relation to a qualifying action has the meaning given in article 66;

capped heating repair measure” means a qualifying action that is—

(a)

the repair of an efficient boiler;

(b)

the repair of equipment for the generation of heat wholly or partly from biofuel, oil or liquefied petroleum gas; or

(c)

the repair of an efficient electric storage heater;

capped heating replacement measure” means a qualifying action that is—

(a)

the replacement of an efficient boiler with another efficient boiler;

(b)

the replacement of an efficient heating system with another efficient heating system of the same kind, other than where the efficient heating system being replaced is—

(i)

a district heating connection; or

(ii)

a renewable heating system;

data light measure allowance” means, in relation to a participant, the number calculated as the participant’s data light measure allowance under article 48 (see articles 71(3) and (4) and 77(2) which provide that this is the maximum number of qualifying actions promoted by the participant which are data light measures of the same data light measure description and in relation to which the annual cost savings may be counted towards the achievement of the participant’s total home-heating cost reduction obligation)(1);

data light measure description” means, in relation to a data light measure, the measure description published by the Administrator in respect of the data light measure under article 41(1)(a);

determined cost savings” means—

(a)

in relation to an ECO4 project that meets the requirements of article 49, the annual cost savings of the project determined in accordance with article 53(2)(b);

(b)

in relation to a basic heating repair or replacement measure, the annual cost savings of the qualifying action determined in accordance with article 67(3);

(c)

in relation to—

(i)

the repair of an efficient electric storage heater; or

(ii)

the replacement of an efficient electric storage heater with another efficient electric storage heater,

the annual cost savings of the qualifying action determined in accordance with article 68(3);

(d)

in relation to a data light measure or a standard alternative methodology measure not falling within paragraph (b) or (c), the annual cost savings of the qualifying action determined in accordance with article 75(2)(c);

(e)

in relation to a DHC alternative methodology measure, the annual cost savings of the qualifying action determined in accordance with the alternative methodology approved by the Administrator under article 70(5);

(f)

in relation to a surplus action or an ECO3 interim delivery action, the annual cost savings of the qualifying action determined in accordance with article 78(2);

(g)

in relation to a qualifying action not falling within paragraphs (b) to (f), the annual cost savings of the qualifying action determined in accordance with article 76(2)(c);

“DHCalt” is, in relation to a DHC alternative methodology measure, the determined cost savings for the qualifying action;

DHC alternative methodology measure” means a qualifying action which is the installation of a district heating connection in respect of which the Administrator has approved an alternative methodology under article 70(5);

“DHCstandard” is, in relation to a DHC alternative methodology measure, the annual cost savings of the qualifying action determined in accordance with article 76(2)(c);

energy cost rating equations” means the equations set out in chapter 13 of the Standard Assessment Procedure;

exempted ECO4 project” means an ECO4 project that meets condition B in article 50(3);

exempted project allowance” means, in relation to a participant, the number calculated as the participant’s exempted project allowance under article 48 (see article 50(1)(b) and (5) which provide that this is the maximum number of ECO4 projects promoted by the participant that may meet the minimum requirement for energy efficiency improvement in that article by virtue of meeting condition B in that article);

full project score” means the score given to an ECO4 project that meets the requirements of article 49;

general innovation allowance” means, in relation to a participant, the amount equal to 10% of the participant’s total home-heating cost reduction obligation;

heating repair allowance” means, in relation to a participant, the number calculated as the participant’s heating repair allowance under article 48 (see articles 67(3) and 68(3) which provide that this is the maximum number of ECO3 interim delivery actions and ECO4 projects promoted by the participant which are, or which contain, a capped heating repair measure in relation to which the annual cost savings of the capped heating repair measure may be counted towards the achievement of the participant’s total home-heating cost reduction obligation);

heating replacement allowance” means, in relation to a participant, the number calculated as the participant’s heating replacement allowance under article 48 (see articles 67(3) and 68(3) which provide that this is the maximum number of surplus actions, ECO3 interim delivery actions and ECO4 projects promoted by the participant which are, or which contain, a capped heating replacement measure in relation to which the annual cost savings of the capped heating replacement measure may be counted towards the achievement of the participant’s total home-heating cost reduction obligation);

innovation measure uplift”, in relation to an innovation measure, is the amount calculated in accordance with article 58(4);

partial project score” means the score given to a qualifying action which is part of an ECO4 project that does not meet the requirements of article 49;

positive score” means a score which is greater than zero;

post-project energy efficiency assessment” means, in relation to an ECO4 project, a SAP assessment or an RdSAP assessment performed after the completion of the project;

project innovation uplift” has the meaning given in article 55(3) (see the definition of “IMP” in that article);

uplift eligible innovation measure” has the meaning given in article 60(2).

(1)

See also articles 51(2)(a) and 53, which provide that the data light measure allowance sets a maximum for the number of qualifying actions promoted by the participant which are data light measures of the same data light measure description and in relation to which the adjusted cost savings may be used in the determination of the post-project SAP band under article 51(1)(a)(ii), and in the determination of the post-project SAP rating under article 53(3)(a)(ii).

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Impact Assessments

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources