76.—(1) The Administrator must publish, on its website, a methodology for the purpose of determining the annual cost savings of a qualifying action other than a data light measure, a standard alternative methodology measure, a basic heating repair or replacement measure or a qualifying action referred to in article 68(1)(b).
(2) Under the methodology published by the Administrator—
(a)the initial determination of the annual cost savings must—
(i)be based on—
(aa)the pre-project SAP rating; and
(bb)the impact the qualifying action would have on the SAP rating of the domestic premises; and
(ii)where the qualifying action is the installation of cavity wall insulation or loft insulation, which forms part of an ECO4 project which includes an item of work—
(aa)to which article 62(2) applies; and
(bb)which is the extraction of cavity wall insulation or loft insulation,
take into account any impact that work would have on the SAP rating of the domestic premises as compared to the pre-project SAP rating;
(b)the result of the initial determination referred to in sub-paragraph (a) must be reduced by 10 % in order to calculate the adjusted cost savings; and
(c)the annual cost savings must finally be determined in accordance with the following formula—
AKM + (IKM x F).
(3) In paragraph (2)(c)—
“AKM” is the adjusted cost savings calculated in accordance with paragraph (2)(b);
“IKM” is the initial determination of the annual cost savings referred to in paragraph (2)(a).
(4) Before publishing a methodology under this article, the Administrator must have regard to the Standard Assessment Procedure and the Reduced Data Standard Assessment Procedure.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: