SECTION 2Additional requirements for heating measures

Additional requirements to be met by heating measures

26.  A heating measure meets the requirements of this article if—

(a)it meets the requirements of article 27 (general requirements relating to heating measures); and

(b)where the measure is—

(i)installed at on-gas premises, it meets the requirements of article 28 (requirements specific to on-gas premises);

(ii)installed at off-gas premises, it meets the requirements of article 29 (requirements specific to off-gas premises).

General requirements relating to heating measures

27.—(1) A heating measure meets the requirements of this article if—

(a)the measure is not—

(i)the installation of equipment for the generation of heat wholly or partly from coal; or

(ii)the installation of a connection to a district heating system that delivers heat generated wholly or partly from coal;

(b)where the measure is the installation of equipment for the generation of heat wholly or partly from biofuel, oil or liquefied petroleum gas, the measure—

(i)is installed at off-gas premises;

(ii)is a repair of a central heating system; and

(iii)complies with the off-gas heating hierarchy in article 30;

(c)where the measure is the installation of a connection to a district heating system that delivers heat generated wholly or partly from biofuel, oil or liquefied petroleum gas, the measure—

(i)is installed at off-gas premises;

(ii)is a repair of the district heating connection; and

(iii)complies with the off-gas heating hierarchy in article 30;

(d)where the measure is the installation of equipment for the generation of heat wholly or partly from mains gas, or the installation of a connection to a district heating system that delivers heat generated wholly or partly from mains gas, the measure is installed at on-gas premises;

(e)where the measure is the installation of an electric storage heater, but is not a repair, the measure—

(i)has a responsiveness rating equal to, or greater than, 0.8 when assessed against the Standard Assessment Procedure; and

(ii)replaces an electric heating system at the premises or is installed at premises where one or more electric storage heaters are already installed;

(f)where the measure is the installation of an electric heating system, but is not a repair, the measure—

(i)has a responsiveness rating equal to, or greater than, 0.8 when assessed against the Standard Assessment Procedure; and

(ii)replaces an electric heating system at the premises or is installed at premises where one or more electric storage heaters are already installed;

(g)where the measure is the installation of a central heating system or a district heating connection not referred to in sub-paragraph (f), but is not a repair, the measure is an efficient heating system;

(h)where the measure is the installation of a boiler, but is not a repair—

(i)it is an efficient boiler; and

(ii)where the boiler forms part of a wet central heating system, hydraulic balancing of the central heating system is carried out following the installation of the boiler;

(i)where the measure includes the installation of equipment for the direct conversion of sunlight into electricity, the measure is installed at domestic premises—

(i)at which there is already installed—

(aa)a hydronic heat pump; or

(bb)an electric storage heater or an electric heating system that in either case has a responsiveness rating equal to, or greater than, 0.8 when assessed against the Standard Assessment Procedure; or

(ii)at which there is installed as part of the same ECO4 project as the measure—

(aa)a hydronic heat pump;

(bb)an electric storage heater, that meets the requirements of sub-paragraph (e)(i) and (ii); or

(cc)an electric heating system, that meets the requirements of sub-paragraph (f)(i) and (ii);

(j)where the measure is the installation of equipment for the generation of heat wholly or partly from biomass, the measure—

(i)is installed at premises which are in a rural area; and

(ii)generates heat from biomass which is wholly woodfuel; and

(k)where the measure is the replacement of an efficient boiler with another efficient boiler, the boiler being replaced is broken down and is not economically repairable.

(2) In paragraph (1)—

hydraulic balancing” means the carrying out of steps to ensure the temperature difference is the same between the inlet and outlet of each radiator, or other heat emitter, in a heating system;

mains gas” means a supply of the kind mentioned in section 5(1)(b) of the Gas Act 1986(1);

woodfuel” has the same meaning as in paragraph 6 of Schedule 4A to the Renewable Heat Incentive Scheme Regulations 2018(2).

Requirements specific to heating measures installed at on-gas premises

28.—(1) A heating measure installed at on-gas premises meets the requirements of this article if—

(a)where the measure is installed at premises which, immediately prior to the installation of the measure, have an efficient heating system which is not broken down, the measure—

(i)is—

(aa)a renewable heating system;

(bb)a district heating connection;

(cc)the installation of heating controls; or

(dd)an innovation measure; and

(ii)in the case of a replacement of the efficient heating system, is not a measure of the same kind as the heating system that is being replaced;

(b)where the measure is installed at premises which, immediately prior to the installation of the measure, have an efficient heating system which is broken down and can be economically repaired, the measure—

(i)is—

(aa)a renewable heating system;

(bb)a district heating connection;

(cc)the installation of heating controls;

(dd)an innovation measure; or

(ee)a repair of the heating system; and

(ii)in the case of a replacement of the efficient heating system, is not a measure of the same kind as the heating system that is being replaced;

(c)where the measure is installed at premises which, immediately prior to the installation of the measure, have an efficient heating system which is broken down and is not economically repairable, the measure—

(i)is—

(aa)a boiler, if the efficient heating system is broken down because a boiler forming part of that heating system is broken down;

(bb)a renewable heating system;

(cc)a district heating connection;

(dd)a central heating system;

(ee)an electric storage heater, but only if the efficient heating system which is broken down is an electric heating system or an electric storage heater;

(ff)the installation of heating controls; or

(gg)an innovation measure; and

(ii)is not a repair of the efficient heating system;

(d)where the measure is installed at premises which, immediately prior to the installation of the measure, have an inefficient heating system (whether or not broken down), the measure—

(i)is—

(aa)a boiler;

(bb)a renewable heating system;

(cc)a district heating connection;

(dd)a central heating system;

(ee)an electric storage heater, but only if the inefficient heating system which is broken down is an electric heating system or an electric storage heater;

(ff)the installation of heating controls; or

(gg)an innovation measure; and

(ii)is not a repair of the inefficient heating system; and

(e)where the measure is installed at premises which, immediately prior to the installation of the measure, have neither an efficient heating system nor an inefficient heating system, the measure is—

(i)a wet central heating system;

(ii)a renewable heating system;

(iii)a district heating connection;

(iv)the installation of heating controls; or

(v)an innovation measure.

(2) A heating measure installed at on-gas premises also meets the requirements of this article if—

(a)the measure forms part of an ECO4 project which includes the installation of a district heating connection which meets the requirements of paragraph (1); and

(b)the measure is a wet central heating system installed after the completion of the installation of the district heating connection.

Requirements specific to heating measures installed at off-gas premises

29.—(1) A heating measure installed at off-gas premises meets the requirements of this article if—

(a)where the measure is installed at premises which, immediately prior to the installation of the measure, have an efficient heating system which is not broken down, the measure is—

(i)a measure that complies with the off-gas heating hierarchy in article 30, but in the case of a replacement of the efficient heating system, is not a measure of the same kind as the heating system being replaced;

(ii)the installation of heating controls; or

(iii)an innovation measure, but in the case of a replacement of the efficient heating system, is not a measure of the same kind as the heating system being replaced;

(b)where the measure is installed at premises which, immediately prior to the installation of the measure, have an efficient heating system which is broken down and can be economically repaired, the measure is—

(i)a repair of the efficient heating system, if the heating system is not fuelled by coal, biofuel, oil or liquefied petroleum gas;

(ii)a measure—

(aa)that complies with the off-gas heating hierarchy in article 30;

(bb)which, in the case of a replacement of the efficient heating system, is not a measure of the same kind as the heating system being replaced; and

(cc)which is not a repair of the efficient heating system, unless it is a measure that complies with the off-gas heating hierarchy in article 30 by virtue of being a measure referred to in article 30(2)(c)(ii);

(iii)the installation of heating controls; or

(iv)an innovation measure, but in the case of a replacement of the efficient heating system, is not a measure of the same kind as the heating system being replaced;

(c)where the measure is installed at premises which, immediately prior to the installation of the measure, have either an efficient heating system which is broken down and is not economically repairable or an inefficient heating system (whether or not broken down), the measure—

(i)is—

(aa)a measure that complies with the off-gas heating hierarchy in article 30;

(bb)the installation of heating controls; or

(cc)an innovation measure; and

(ii)is not a repair unless it is a measure that complies with the off-gas heating hierarchy in article 30 by virtue of being a measure referred to in article 30(2)(c)(ii); and

(d)where the measure is installed at premises which, immediately prior to the installation of the measure, have neither an efficient heating system nor an inefficient heating system, the measure is—

(i)a measure that complies with the off-gas heating hierarchy in article 30;

(ii)the installation of heating controls; or

(iii)an innovation measure.

(2) A heating measure installed at off-gas premises also meets the requirements of this article if—

(a)the measure—

(i)forms part of an ECO4 project which includes the installation of a district heating connection which meets the requirements of paragraph (1); and

(ii)is a wet central heating system installed after the completion of the installation of the district heating connection; or

(b)the measure—

(i)is a repair of a renewable heating system; and

(ii)the heating system being repaired is not an inefficient heating system.

Hierarchy of heating measures installed at off-gas premises

30.—(1) A measure complies with the off-gas heating hierarchy if it is a measure to which paragraph (2) applies.

(2) This paragraph applies to a measure which is—

(a)one of the following—

(i)a hydronic heat pump;

(ii)a wet central heating system which generates heat wholly from a hydronic heat pump; or

(iii)a connection to a district heating system that delivers heat generated wholly from a hydronic heat pump;

(b)if it is not possible to install any of the measures referred to in sub-paragraph (a) at the premises, either—

(i)a district heating connection (other than a district heating connection referred to in sub-paragraph (a)(iii)); or

(ii)if the premises are in a rural area, the installation of equipment for the generation of heat wholly or partly from biomass; or

(c)if it is not possible to install at the premises any of the measures referred to in sub-paragraphs (a) or (b), one of the following—

(i)if the heating system at the premises immediately prior to the installation of the measure is an electric heating system or an electric storage heater—

(aa)an electric heating system; or

(bb)an electric storage heater;

(ii)the repair of—

(aa)a renewable heating system which is an inefficient heating system;

(bb)a central heating system which is fuelled wholly or partly from biofuel, oil or liquefied petroleum gas; or

(cc)a connection to a district heating system that delivers heat generated wholly or partly from biofuel, oil or liquefied petroleum gas.

(3) For the purposes of paragraph (2), it is “not possible” to install a measure—

(a)if it is not reasonably practicable to install the measure;

(b)if it attracts an exemption under Part 11;

(c)if the measure is the installation of equipment for the generation of heat wholly or partly from biomass and the premises are not in a rural area;

(d)if—

(i)one or more improvement options evaluation reports in relation to the premises are held on the TrustMark Data Warehouse; and

(ii)the measure is not amongst the measures recommended in the most recent improvement options evaluation report; or

(e)if—

(i)no improvement options evaluation report in relation to the premises is held on the TrustMark Data Warehouse;

(ii)one or more EPC recommendation reports have been issued for the premises; and

(iii)the measure is not amongst the measures recommended in the most recent EPC recommendation report.

(4) In this article—

EPC recommendation report” means a recommendation report included in an energy performance certificate, and for the purposes of this definition, “recommendation report”—

(a)

in relation to domestic premises in England and Wales, has the meaning given in regulation 4(1) of the Energy Performance of Buildings (England and Wales) Regulations 2012(3);

(b)

in relation to domestic premises in Scotland, has the same meaning as “recommendations report” in regulation 6A of the Energy Performance of Buildings (Scotland) Regulations 2008(4);

improvement options evaluation report” means a report by a retrofit coordinator prepared under clause 9.2.6 of PAS 2035:2019 that recommends measures to improve the energy performance of the domestic premises;

retrofit coordinator” has the meaning given in clause 3.26 of PAS 2035:2019.

(1)

Section 5 was substituted by section 3(1) of the Gas Act 1995 (c. 45). Relevant amendments were made by section 108 of, and Schedule 2 to, the Utilities Act 2000 and S.I. 2012/2400.

(2)

S.I. 2018/611, amended by S.I. 2021/76. There are other amending instruments, but none is relevant.

(3)

S.I. 2012/3118. Section 4(1) was amended by S.I. 2013/181.

(4)

S.S.I. 2008/309. Regulation 6A was inserted by S.S.I. 2012/208, and amended by S.S.I. 2013/12.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Impact Assessments

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources