238.—(1) The undertaker will notify the of relevant local highway authority -
(a)of the anticipated date of commencement of any Works to be undertaken under this Order; and
(b)of the anticipated construction programme and date of completion of the authorised development;
not less than 3 months prior to that anticipated date of commencement of any Works to be undertaken under this Order.
(2) The undertaker and relevant local highway authority may agree that the relevant local highway authority will procure the highway condition surveys required under this Part of this Schedule at the cost of the undertaker.
(3) The undertaker will agree a proposed scope with the relevant local highway authority setting out the number (having regard to the construction programme), content and format of the highway condition surveys no later than 4 weeks after notification under sub- paragraph (1). If the undertaker fails to provide a highway condition survey or does not provide the relevant local highway authority with sufficient time to undertake a highway condition survey prior to any Works being undertaken pursuant to the Order then in default the last highway condition survey undertaken by the relevant local highway authority will amount to the baseline condition of the relevant highway and/or highway asset.
(4) A final highway condition survey must be procured by the undertaker within 28 days of the relevant local highway authority being notified by the undertaker that the construction of the authorised development is complete.
(5) Copies of any highway condition survey carried out in accordance with this paragraph must be provided to the relevant local highway authority by the undertaker within 10 working days of the completion of the relevant survey.
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Schedule you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Schedule you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: