The Town and Country Planning (Development Management Procedure) (Wales) Order 2012

Changes to legislation:

There are currently no known outstanding effects for the The Town and Country Planning (Development Management Procedure) (Wales) Order 2012, Section 22. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Time periods for decisionsE+W

22.—(1) Subject to paragraph (5), where a valid application has been received by a local planning authority, they must within the period specified or referred to in paragraph (2) M1 give the applicant notice of their decision or determination or give notice that the application has been referred to the Welsh Ministers.

[F1(1A) References in paragraph (1) to a valid application include references to that application as amended prior to the local planning authority determining the application.]

(2) The period specified or referred to in this paragraph is—

(a)the period of eight weeks beginning with the date on which the application was received by the local planning authority;

[F2(aa)in a case to which paragraph (1A) applies, the period of —

(i)4 weeks beginning with the date on which the amendment to the application was received by the authority; or

(ii)12 weeks beginning with the date on which the application to which the amendment relates is received by the authority

whichever is the later;]

(b)except where the applicant has already given notice of appeal to the Welsh Ministers, such extended period as may be agreed in writing between the applicant and the authority; or

(c)where any fee required in respect of an application has been paid by a cheque which is subsequently dishonoured, the appropriate period [F3specified in sub-paragraphs (a), (aa) or (b)] calculated disregarding the period between the date when the authority sent the applicant written notice of the dishonouring of the cheque and the date when the authority are satisfied they have received the full amount of the fee.

(3) In this article “valid application” (“cais dilys”) means an application which consists of—

[F4(a)an application which complies with the requirements of article 5;]

(b)where an application is made in respect of Crown land, the documents required by article 6;

[F5(ba)in a case to which article 2F applies, the pre-application consultation report required by that article;]

(c)in a case to which article 7 applies, the design and access statement F6...;

(d)in a case to which article 9 applies, the written declaration required by that article;

(e)the certificate required by article 11;

(f)subject to paragraph (4), the particulars or evidence required by the local planning authority under section 62(3) of the 1990 Act (applications for planning permission) M2; and

(g)any fee required to be paid in respect of the application and, for this purpose, lodging a cheque for the amount of the fee is to be taken as payment,

and a valid application must be taken to have been received when the application and such of the documents, particulars or evidence referred to above as are required to be included in or to accompany the application and any fee required have been lodged with the local planning authority.

[F7(3A) An amendment to a valid application must be taken to have been received when the amendment and such of the documents included in or accompanying the amendment and any fee required have been lodged with the local planning authority.]

(4) Paragraph (3)(f) only applies if—

(a)the application is for major development;

(b) before the application is made the local planning authority publish, for the purposes of paragraph (3), a list of requirements on their website; and

(c)the particulars or evidence that the authority require to be included in the application fall within that list.

(5) A local planning authority must provide such information about applications made under article 4 or article 5 (including information as to the manner in which any such application has been dealt with) as the Welsh Ministers may by direction require. Any such direction may include provision as to the persons to be informed and the manner in which the information is to be provided.

(6) Subject to paragraph (7), a local planning authority must not determine an application for planning permission, where any notice of, or information about, the application has been—

(a)given by site display under article 10 or 12, before the end of the period of 21 days [F8or, in the case of an EIA application accompanied by an environmental statement 30 days, in either case] beginning with the date when the notice was first displayed by site display;

[F9(b)served on or given to—

(i)an owner of the land or a tenant under article 10, or

(ii)an adjoining owner or occupier under article 12,

before the end of the period of 21 days beginning with the date when the notice was served on or given to that person; or]

(c)published in a newspaper under article 10 or 12 or on a website under article 12, within the period of 14 days [F10or, in the case of an EIA application accompanied by an environmental statement 30 days, in either case] beginning with the date on which the notice or information was published,

M3and the periods in this paragraph are periods prescribed for the purposes of section 71(1) of the 1990 Act (consultations in connection with determinations under section 70) .

(7) Where, under paragraph (6), more than one of the prescribed periods applies, the local planning authority must not determine the application before the end of the later or latest of such periods.

Textual Amendments

Modifications etc. (not altering text)

C1Arts. 22, 23 modified by S.I. 2016/58, reg. 57(2) (as substituted (7.11.2016) by The Town and Country Planning (Environmental Impact Assessment) (Wales) (Amendment) Regulations 2016 (S.I. 2016/971), regs. 1(2), 2 (with reg. 3))

Marginal Citations

M1S.I. 1999/293 extends the time period for determination of applications for EIA development.

M2Section 62 was substituted by section 42(1) of the 2004 Act.

M3Section 71(1) was substituted by section 16(2) of the Planning and Compensation Act 1991 (c. 34).

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area. The revised version is currently only available in English.

Original (As Enacted or Made) - English: The original English language version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Original (As Enacted or Made) - Welsh:The original Welsh language version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources