Search Legislation

The Sustainable Drainage (Approval and Adoption Procedure) (Wales) Regulations 2018

 Help about what version

What Version

 Help about opening options

Opening Options

Status:

This is the original version (as it was originally made). This item of legislation is currently only available in its original format.

PART 4Where duty to adopt does not apply

Single property exception

9.  For the purposes of paragraph 18(1) or (2) of Schedule 3 a drainage system or any part of a drainage system is to be treated as designed only to provide drainage for a single property if it is designed to provide drainage for any buildings or other structures that, following completion of the construction work, will be owned, managed or controlled by—

(a)a single person, or

(b)two or more persons together.

Release of non-performance bond where duty to adopt does not apply

10.—(1) Except where paragraph (3) applies, an approving body must release a non-performance bond within 4 weeks beginning on the first working day after completion of a drainage system that is constructed in accordance with approved proposals.

(2) Paragraph (3) applies if the approving body—

(a)issued a certificate under paragraph 12(2) of Schedule 3, and

(b)carried out work to ensure the drainage system was completed in such a manner as to make it likely to operate in compliance with national standards.

(3) The approving body must, within 4 weeks beginning on the first working day after completing the work—

(a)send to the developer a full account of any sums received under the bond that have been applied to the expense of carrying out the work,

(b)pay the developer any excess, and

(c)release the non-performance bond.

(4) In this regulation—

“approved proposals” (“cynigion a gymeradwywyd”) means proposals approved under paragraph 7(1) of Schedule 3, including any conditions of approval;

“drainage system” (“system ddraenio”) is to be construed as a drainage system to which the duty to adopt does not apply.

Notification of voluntary adoption

11.—(1) An approving body must give any notification under paragraph 24(2) of Schedule 3 as soon as practicable after deciding to adopt a drainage system to which the duty to adopt does not apply.

(2) The notification must specify—

(a)the reason for adoption, and

(b)the date of adoption.

Registration and designation following voluntary adoption

12.  Within 4 weeks beginning on the first working day after giving a notification under paragraph 24(2) of Schedule 3, an approving body must arrange for—

(a)the lead local flood authority to include the drainage system in the register maintained under section 21 of the Act, and

(b)a designating authority to make a provisional designation under paragraph 7 of Schedule 1 of any part of the drainage system (whether an adopted part or not) which is eligible for designation and is not owned by the approving body.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area. The revised version is currently only available in English.

Original (As Enacted or Made) - English: The original English language version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Original (As Enacted or Made) - Welsh:The original Welsh language version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources