Changes to legislation:

The Public Contracts Regulations 2015, Section 32 is up to date with all changes known to be in force on or before 14 May 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.

View outstanding changes

Changes and effects yet to be applied to Regulation 32:

Changes and effects yet to be applied to the whole Instrument associated Parts and Chapters:

Whole provisions yet to be inserted into this Instrument (including any effects on those provisions):

  • reg. 6(15A) words omitted by S.I. 2023/506 reg. 2(3)(a) (This amendment not applied to legislation.gov.uk. S.I. 2023/506 revoked before coming into force by The Public Procurement (International Trade Agreements) (Amendment) (Wales) (No. 2) Regulations 2023 (S.I. 2023/567), regs. 1(2), 6)
  • reg. 10(1)(d)(i)(aa) words substituted by S.I. 2019/560 reg. 5(9)(a)(i) (This amendment not applied to legislation.gov.uk. Affecting Regulations revoked (20.11.2020) by S.I. 2020/1319, regs. 1(3), 2(a))
  • reg. 10(1)(d)(i)(bb) words substituted by S.I. 2019/560 reg. 5(9)(a)(ii) (This amendment not applied to legislation.gov.uk. Affecting Regulations revoked (20.11.2020) by S.I. 2020/1319, regs. 1(3), 2(a))
  • reg. 18(4) words omitted by S.I. 2023/506 reg. 2(4) (This amendment not applied to legislation.gov.uk. S.I. 2023/506 revoked before coming into force by The Public Procurement (International Trade Agreements) (Amendment) (Wales) (No. 2) Regulations 2023 (S.I. 2023/567), regs. 1(2), 6)
Use of the negotiated procedure without prior publicationU.K.
This section has no associated Explanatory Memorandum

32.—(1) In the specific cases and circumstances laid down in this regulation, contracting authorities may award public contracts by a negotiated procedure without prior publication.

General grounds

(2) The negotiated procedure without prior publication may be used for public works contracts, public supply contracts and public service contracts in any of the following cases:—

(a)where no tenders, no suitable tenders, no requests to participate or no suitable requests to participate have been submitted in response to an open procedure or a restricted procedure, provided that the initial conditions of the contract are not substantially altered [F1and that—

(i)a report is sent to the Cabinet Office if it so requests;

(ii)where the contracting authority is a devolved Welsh authority, a report is sent to the Welsh Ministers if they so request (whether or not the Cabinet Office also makes a request under paragraph (i));

(iii)where the contracting authority is a devolved Northern Ireland authority, a report is sent to a Northern Ireland department if that department so requests (whether or not the Cabinet Office also makes a request under paragraph (i));]

(b)where the works, supplies or services can be supplied only by a particular economic operator for any of the following reasons:—

(i)the aim of the procurement is the creation or acquisition of a unique work of art or artistic performance,

(ii)competition is absent for technical reasons,

(iii)the protection of exclusive rights, including intellectual property rights,

but only, in the case of paragraphs (ii) and (iii), where no reasonable alternative or substitute exists and the absence of competition is not the result of an artificial narrowing down of the parameters of the procurement;

(c)insofar as is strictly necessary where, for reasons of extreme urgency brought about by events unforeseeable by the contracting authority, the time limits for the open or restricted procedures or competitive procedures with negotiation cannot be complied with.

(3) For the purposes of paragraph (2)(a)—

(a)a tender shall be considered not to be suitable where it is irrelevant to the contract, being manifestly incapable, without substantial changes, of meeting the contracting authority's needs and requirements as specified in the procurement documents;

(b)a request to participate shall be considered not to be suitable where the economic operator concerned—

(i)is to be or may be excluded under regulation 57, or

(ii)does not meet the selection criteria.

(4) For the purposes of paragraph (2)(c), the circumstances invoked to justify extreme urgency must not in any event be attributable to the contracting authority.

Additional grounds relevant to public supply contracts

(5) The negotiated procedure without prior publication may be used for public supply contracts—

(a)where the products involved are manufactured purely for the purpose of research, experimentation, study or development, but contracts awarded in reliance on this sub-paragraph shall not include quantity production to establish commercial viability or to recover research and development costs;

(b)for additional deliveries by the original supplier which are intended either as a partial replacement of supplies or installations or as the extension of existing supplies or installations where a change of supplier would oblige the contracting authority to acquire supplies having different technical characteristics which would result in incompatibility or disproportionate technical difficulties in operation and maintenance;

(c)for supplies quoted and purchased on a commodity market;

(d)for the purchase of supplies or services on particularly advantageous terms, from either a supplier which is definitively winding up its business activities, or the liquidator in an insolvency procedure, an arrangement with creditors, or a similar procedure under national laws or regulations.

(6) In the case of paragraph (5)(b), the duration of the contract, as well as that of recurrent contracts, shall not, save in exceptional circumstances, exceed 3 years.

Additional ground relevant to public service contracts that follow a design contest

(7) The negotiated procedure without prior publication may be used for public service contracts where the contract concerned—

(a)follows a design contest organised in accordance with this Part, and

(b)is to be awarded, under the rules provided for in the design contest, to—

(i)the winner of the design contest, or

(ii)one of the winners of the design contest.

(8) Where paragraph (7)(b)(ii) applies, all winners must be invited to participate in the negotiation.

Additional ground relevant to new works or services which repeat similar ones

(9) The negotiated procedure without prior publication may be used for new works and services consisting of the repetition of similar works or services entrusted to the economic operator to which the same contracting authority awarded an original contract, provided that such works or services are in conformity with a basic project for which the original contract was awarded following a procedure in accordance with regulation 26(1) and (2).

(10) The basic project shall indicate the extent of possible additional works or services and the conditions under which they will be awarded.

(11) As soon as the first project is put up for tender, the possible use of this procedure shall be disclosed and the total estimated cost of subsequent works or services shall be taken into consideration by the contracting authority when it applies regulation 5.

(12) This procedure may be used only during the 3 years following the conclusion of the original contract.

Textual Amendments

Back to top

Options/Help

Print Options

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources