Search Legislation

The Ferrybridge Multifuel 2 Power Station (Amendment) Order 2018

Status:

This is the original version (as it was originally made). This item of legislation is currently only available in its original format.

Citation and commencement

1.  This Order may be cited as the Ferrybridge Multifuel 2 Power Station (Amendment) Order 2018 and comes into force on 20th September 2018.

Amendment to the Ferrybridge Multifuel 2 Power Station Order 2015

2.  The Ferrybridge Multifuel 2 Power Station Order 2015 (“the 2015 Order”) is amended in accordance with this Order.

Certification of revised documents

3.—(1) The undertaker must, as soon as practicable after the making of this Order, submit to the Secretary of State copies of the documents listed in paragraph (2) that were submitted with the application for a non-material change of 11th January 2018, for certification that they are true copies of those documents.

(2) The documents referred to in paragraph (1) are—

(a)the revised biodiversity strategy;

(b)the revised indicative landscaping plan; and

(c)the revised landscaping strategy.

(3) A document certified by the Secretary of State under this article is admissible in any proceedings as evidence of the contents of the document of which it is a copy.

(4) For the purposes of the 2015 Order, where a document is certified under this article, then it must be treated as having replaced any equivalent document certified earlier under article 23 of the 2015 Order.

(5) In paragraph (1), the “undertaker” has the same meaning as in article 2(1) of the 2015 Order.

Amendments to Schedule 2 (Requirements)

4.—(1) Schedule 2 (Requirements) is amended as set out in the table in the Schedule to this Order, in which—

(a)column 1 sets out where the amendment is made;

(b)column 2 sets out how the amendment is to be made; and

(c)column 3 sets out the text to be substituted or inserted.

(2) The Schedule to this Order has effect.

Signed by authority of the Secretary of State for Business, Energy and Industrial Strategy

Gareth Leigh

Head of Energy Infrastructure Planning

Department for Business, Energy and Industrial Strategy

19th September 2018

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources