Article 34
(1) Area | (2) Number of plot shown on land plans | (3) Purpose for which temporary possession may be taken | (4) Relevant part of authorised development |
---|---|---|---|
Cheshire and Chester West | 1-05 | Temporary use as a construction working area and for access (as part of Work No.3) | Work Nos 1, 2, 3, 3A, 3B 4 and 5 |
Cheshire and Chester West | 1-06d | Temporary use as a construction access (Work No.3A) | Work Nos 1, 2, 3, 3A, 3B, 4 and 5 |
Cheshire and Chester West | 1-08 | Temporary use as a construction compound and working area (as part of Work No.1A) | Work Nos 1, 2, 3, 4 and 5 |
Cheshire and Chester West | 1-16, 1-17 | Temporary use as construction access (as part of Work No.3) | Work Nos 1, 2, 3, 4 and 5 |
Cheshire and Chester West | 2-02 | Temporary use as a construction working area and for access to facilitate construction (as part of Work No.5C) | Work Nos 2, 3, 4 and 5 |
Cheshire and Chester West | 2-04 | Temporary use as a construction access (as part of Work No.5C) | Work Nos 2, 3, 4, 5 and 6 |
Cheshire and Chester West | 2-07 | Temporary use as a construction access (as part of Work No.5A) | Work Nos 2, 3, 4, 5 and 6 |
Cheshire and Chester West | 2-11, 2-12 | Temporary use a construction access (as part of Work No.5B) | Work Nos 2, 3, 4, 5 and 6 |
Cheshire and Chester West | 3-01 | Temporary use as a construction access (Work No. 6C) | Work Nos 4, 5, 6, 7 and 11 |
Cheshire and Chester West | 3-02 | Temporary use as a construction compound and working area (as part of Work No. 6B) | Work Nos 4, 5, 6, 7, 11, 57A and 57B |
Cheshire and Chester West | 4-01, 4-02 | Temporary use as a construction compound and working area (as part of Work No. 6B) | Work Nos 4, 5, 6, 7, 11, 57A and 57B |
Cheshire and Chester West | 4-03, 4-04 | Temporary use for a construction access including visibility splay (as part of Work No. 6D) | Work Nos 4, 5, 6, 7, 11, 57A and 57B |
Cheshire and Chester West | 4-11 | Temporary use as a construction access (Work No. 6E) | Work Nos 4, 5, 6, 7, 11, 57A and 57B |
Cheshire and Chester West | 5-03, 5-04 | Temporary use as a construction access (as part of Work No 12) | Work Nos 11, 12, 13, 14, 57C and 57D |
Cheshire and Chester West | 5-19, 5-21, 5-24, 5-25, 5-26, 6-11, 6-13 | Temporary use for access and peat storage | Work Nos 13, 13A, 14, 57E and 57F |
Cheshire and Chester West | 6-20 | Temporary use as a construction compound and working area (as part of Work No. 15A) | Work Nos 14, 15 and 16 |
Cheshire and Chester West | 6-21 | Temporary use as a construction access (Work No.15B) | Work Nos 14, 15 and 16 |
Cheshire and Chester West | 7-02, 7-02a, 7-03b | Temporary use as a construction access (Work No.16B) | Work No. 16A |
Cheshire and Chester West | 7-10 | Temporary use as a working area (as part of Work No. 17) | Work No. 17 |
Cheshire and Chester West | 8-02 | Temporary use as a construction working are and access (Work No. 18A) | Work Nos. 17, 18, 19, 19A, 20 and 21 |
Cheshire and Chester West | 8-06, 8-08 | Temporary use as a construction working area (Work No. 18) | Work Nos. 18, 19, 19A, 20 and 21 |
Cheshire and Chester West | 8-09 | Temporary use as a construction access, compound and working area (Work Nos.19A and 19B) | Work Nos. 17, 18, 19, 19A, 20 and 21 |
Cheshire and Chester West | 8-14 | Temporary use as a construction access (Work No. 19C) | Work Nos. 20 and 21 |
Cheshire and Chester West | 9-02, 9-05, 9-06, 9-08, 9-11, 9-13 | Temporary use as a construction access and working area (as part of Work No. 22) | Work Nos. 19, 22, 23, 24 and 57G |
Cheshire and Chester West | 9-18 | Temporary use as a construction access (Work No. 23A) | Work Nos. 19, 22, 23 and 24 |
Cheshire and Chester West | 9-20 | Temporary use as a construction access and working area (as part of Work No. 23B) | Work Nos. 22, 23 and 24 |
Cheshire and Chester West | 9-23 | Temporary use as a construction access (as part of Work No.24A) | Work Nos. 24 and 25 |
Cheshire and Chester West | 10-04a | Temporary possession for traffic management | Work No. 25 |
Cheshire and Chester West | 10-14 10-15 | Temporary use as a construction access (as part of Work No.25) | Work Nos. 25, 26, 27, 28 |
Cheshire and Chester West | 10-17 | Temporary use as a construction access (Work No.28A) | Work Nos. 25, 26, 26A, 27, 28, 28A, 28B |
Cheshire and Chester West | 10-19 | Temporary use as a construction access and working area (as part of Work Nos.25, 26, 26A and 27 | Work Nos. 25, 26, 26A, 27 and 28 |
Cheshire and Chester West | 11-01, 11-02 | Temporary use as a construction access (Work No.28A) | Work Nos. 25, 26, 26A, 27, 28, 28A, 28B |
Flintshire | 12-12a, 12-13 | Temporary use as a construction compound and working area (as part of Work Nos. 29A and 30A) | Work Nos. 28, 29. 29A, 30 and 30A |
Flintshire | 12-15, 12-16, 12-17 | Temporary use as a construction access (Works No.30 and 30A) | Work Nos. 28, 29, 29A, 30 and 30A |
Flintshire | 13-14, 13-16 | Temporary use as a construction compound and working area (as part of Work No. 30D) | Work Nos. 30 and 31 |
Flintshire | 13-19 | Temporary use as a construction access (as part of Work No.30E) | Work Nos. 30 and 31 |
Flintshire | 14-01 | Temporary use as a construction compound and working area (as part of Work No. 30D) | Work Nos. 30 and 31 |
Flintshire | 14-14 | Temporary use as a construction compound and working area (as part of Work Nos. 31A and 31B) | Work Nos. 30, 31, 32 and 33 |
Flintshire | 14-23, 14-24, 14-25, 14-26, 14-27 | Temporary use as a construction access and working area (as part of Work No. 31B) | Work Nos. 30, 31, 31A, 32 and 33 |
Flintshire | 14-30a, 15-01a | Temporary use as a construction access (as part of Work No.33) | Work No. 33 |
Flintshire | 15-02 | Temporary use as a construction access and working area (as part of Work No.33) | Work Nos.32, 33 and 33A |
Flintshire | 16-01, 16-06, 16-06a, 16-07, 16-08, 16-09, 16-11 | Temporary use as a construction access and working area, and for diversion of public right of way and watercourse (as part of Work No. 34) | Work Nos. 33 and 34 |
Flintshire | 16-17 | Temporary use as a working area (as part of Work No. 34) | Work Nos. 34 and 35 |
Flintshire | 16-28 | Temporary use as a construction working area and access (Work No.35) | Work Nos. 35, 36, 36A and 37 |
Flintshire | 17-05 | Temporary use as a construction access and working area (as part of Work Nos. 35 and 36A) | Work Nos. 35, 36, 36A and 37 |
Flintshire | 17-09, 17-10 | Temporary use as a construction access (Work No.38A) | Work Nos. 35, 36, 36A and 37 |
Flintshire | 17-11 | Temporary use as a working area (as part of Work No. 38) | Work Nos. 37 and 38 |
Flintshire | 17-16 | Temporary use as a construction working area and access (as part of Work No.39B) | Work Nos. 38, 39, 40 and 57H |
Flintshire | 17-31 | Temporary use as a construction access (Work No.39A) | Work Nos. 39, 40 and 57H |
Flintshire | 17-35, 17-37, 17-38 | Temporary use as a construction access and working area (Work No. 40A) | Work Nos. 39, 40 and 57H |
Flintshire | 18-01 | Temporary use as a working area, access and public right of way diversion (as part of Work No. 40B) | Work Nos.40, 41 and 57I |
Flintshire | 18-13 | Temporary use as a construction compound, working area and access (as part of Work Nos. 41A and 41B) | Work Nos. 40, 41, 42 and 57I |
Flintshire | 18-16, 18-17 | Temporary use as a construction access and visibility splay (as part of Work No.41B) | Work Nos. 40, 41, 42 and 57I |
Flintshire | 19-04c | Temporary use as a working area (as part of Work No. 43D) | Work Nos. 42, 43, 57J and 57K |
Flintshire | 20-07 | Temporary use as a working area (as part of Work No. 44) | Work Nos. 44 and 57L |
Flintshire | 20-10, 20-10a | Temporary use as a construction access (as part of Work No.44B) | Work Nos. 44, 44A, 45, 46, 57L and 57M |
Flintshire | 20-16, 20-17 | Temporary use as a construction access (as part of Work No.46) | Work Nos. 44, 44A, 45 and 46 |
Flintshire | 20-19b | Temporary use as a construction access (as part of Work No.45) | Work Nos. 44, 45 and 45B |
Flintshire | 20-20 | Temporary use as a construction compound and working area (as part of Work Nos. 44C and 45A) | Work Nos. 44, 44A, 45, 46, 57L and 57M |
Flintshire | 21-03 | Temporary use as a construction access (Work No.47A) | Work No. 47 |
Flintshire | 21-07 | Temporary use as a construction access (Work No.47B) | Work No. 47 and 48 |
Flintshire | 22-02 | Temporary use as a working area and access (as part of Work No. 47) | Work Nos. 47 and 48 |
Flintshire | 22-04 | Temporary use for and to construct an access (Work No.49) | Work No. 47, 48 and 49 |
Flintshire | 25-03, 25-07, 25-08, 25-09 | Temporary use as a working area (as part of Work Nos. 51a, 51B and 52) | Work Nos. 51, 51A and 52 |
Flintshire | 27-02, 28-01 | Temporary use as a working area (as part of Work Nos. 53A and 53B) | Work Nos. 53, 53A and 54 |
Flintshire | 28-02 | Temporary use for and to construct an access (Work No.54) | Work Nos. 53, 53A and 54 |
Flintshire | 29-01 | Temporary use for and to construct an access (Work No.56) | Work Nos. 55, 55A and 56 |
Flintshire | 29-02 | Temporary use as a working area (as part of Work No. 55B) | Work Nos. 55, 55A and 56 |
Flintshire | 29-06 | Temporary use as a working area (as part of Work Nos. 55A and 55B) | Work Nos. 55, 55A and 56 |
(1) Area | (2) Number of plot shown on land plans | (3) Purpose for which temporary possession may be taken | (4) Relevant part of authorised development |
---|---|---|---|
Cheshire and Chester West | 2-06 | Temporary use for access (as part of Work No.5A) | Work Nos 2, 3, 4, 5 and 6 |
Cheshire and Chester West | 9-24, 9-25 | Temporary use as a construction access (as part of Work No.24A) | Work Nos. 24 and 25 |
Flintshire | 13-13, 13-15, 13-17, 13-18, 14-02, 14-03 | Temporary use as a construction access (as part of Work No.30E) | Work Nos. 30, 30D 31, 31A, 32 and 33 |
Flintshire | 17-34 | Temporary use for access (as part of Work No.40) | Work Nos. 39, 39A, 40, 40A, 41, 57H and 57I |
Flintshire | 19-06 | Temporary use as a construction access (as Work No.43C) | Work Nos. 42, 43, 44, 57J and 57K |
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: